15 U.S.C. § 720e — Judicial review

United States Congress · 2026

Read 15 U.S.C. § 720e — Judicial review by United States Congress (2026) in the Tower of Babel, a free online library of public-domain works preserved in clean, searchable text. No sign-up. The full text is served as a plain-text file at a predictable URL, where text is present: https://antarctic-labs.com/tower-of-babel/uslaw-usc-t15-s720e.txt.

Description

United States Code, Title 15 (Commerce And Trade); Chapter 15D (Alaska Natural Gas Pipeline). Current through Public Law 119-134, as published by the Office of the Law Revision Counsel. (a) Exclusive jurisdiction Except for review by the Supreme Court on writ of certiorari, the United States Court of Appeals for the District of Columbia Circuit shall have original and exclusive jurisdiction to determine— (1) the validity of any final order or action.

Catalog record

CREATORUnited States Congress
YEAR2026
COLLECTIONLAW
FORMATTXT
FILE SIZE2 KB
VERSION1.0
LICENSEPublic Domain
RIGHTSPUBLIC DOMAIN
SOURCEU.S. Code (OLRC)

Source: https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section720e

Browse the full library · About the Tower of Babel

Full text

The opening of the work, from the library's hosted text:

15 U.S.C. § 720e — Judicial review
Citation: us:usc:15:720e
Creator: United States Congress
Year: 2026
Source-URL: https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section720e
Context: United States Code, Title 15 (Commerce And Trade); Chapter 15D (Alaska Natural Gas Pipeline). Current through Public Law 119-134, as published by the Office of the Law Revision Counsel.

(a) Exclusive jurisdiction
Except for review by the Supreme Court on writ of certiorari, the United States Court of Appeals for the District of Columbia Circuit shall have original and exclusive jurisdiction to determine—
(1)
the validity of any final order or action (including a failure to act) of any Federal agency or officer under this chapter;
(2)
the constitutionality of any provision of this chapter, or any decision made or action taken under this chapter; or
(3)
the validity of any determination, permit, approval, authorization, review, or other related action taken under any provision of law relating to a gas transportation project constructed and operated in accordance with section 720a of this title, including—
(A)
subchapter II of chapter 5, and chapter 7, of title 5 (commonly known as the “Administrative Procedure Act”);
(B)
the Endangered Species Act of 1973 (16 U.S.C. 1531 et seq.);
(C)
the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.);
(D)
chapter 2003 of title 54; 1 and
(E)
the Alaska National Interest Lands Conservation Act (16 U.S.C. 3101 et seq.).
(b) Deadline for filing claim
A claim arising under this chapter may be brought not later than 60 days after the date of the decision or action giving rise to the claim.
(c) Expedited consideration
The United States Court of Appeals for the District of Columbia Circuit shall set any action brought under subsection (a) for expedited consideration, taking into account the national interest of enhancing national energy security by providing access to the significant gas reserves in Alaska needed to meet the anticipated demand for natural gas.