An act to extend the deadline under the Federal Power Act for commencement of the construction of the Arrowrock Dam Hydroelectric Project in the State of Idaho.
United States Congress · 2000
Read An act to extend the deadline under the Federal Power Act for commencement of the construction of the Arrowrock Dam Hydroelectric Project in the State of Idaho. by United States Congress (2000) in the Tower of Babel, a free online library of public-domain works preserved in clean, searchable text. No sign-up. The full text is served as a plain-text file at a predictable URL, where text is present: https://antarctic-labs.com/tower-of-babel/plaw-106-343-2000.txt.
Description
Public Law 106-343, approved October 19, 2000, gives a stalled Idaho power project more time to start work. It extends the time limit under the Federal Power Act for building the Arrowrock Dam Hydroelectric Project. The project is Federal Energy Regulatory Commission project number 4656, as the text states in its first section.
In place of the normal span in section 13, the Commission may grant three two-year extensions in a row. The licensee must ask for the added time, and notice must be given first. The law takes effect when the prior grant of time runs out. It also deals with bringing back a license if the time to start had already run out before the act became law.
Catalog record
| CREATOR | United States Congress |
|---|---|
| YEAR | 2000 |
| COLLECTION | DECLASSIFIED |
| FORMAT | TXT |
| FILE SIZE | 2259 |
| LICENSE | Public Domain |
| RIGHTS | PUBLIC DOMAIN |
| SOURCE | Government Publishing Office (govinfo.gov) |