Read U.S. Distribution Transformer Demand Phase III - Key Drivers and Managing Demand [Slides] by McKenna, Killian, Abraham, Sherin Ann, Wang, Wenbo et al. (2026) in the Tower of Babel, a free online library of public-domain works preserved in clean, searchable text. No sign-up. The full text is served as a plain-text file at a predictable URL, where text is present: https://antarctic-labs.com/tower-of-babel/doe-osti-3377667-u-s-distribution-transformer-demand-phas.txt.
Introduction
National Laboratory of the Rockies slides from June 2026 present phase three of a study of United States distribution transformer demand. Four authors are printed: Killian McKenna, Sherin Ann Abraham, Wenbo Wang, and Zephyr Zink, of the laboratory's Distribution Edge and Grid Planning and Analysis Center work. Earlier phases appeared as reports in February 2024 and November 2024.
Distribution transformers step voltage down for electrical service and remain in short supply, with delays and rising prices across the industry. The deck characterizes the transformers now in service, then models future growth. Commercial and industrial demand is driven mainly by new customers and per-capita load growth, while data centers are modeled separately because of their expected scale. A regional analysis and demand management strategies close the deck.
Catalog record
| CREATOR | McKenna, Killian, Abraham, Sherin Ann, Wang, Wenbo et al. |
|---|---|
| YEAR | 2026 |
| COLLECTION | PAPERS |
| FORMAT | TXT |
| FILE SIZE | 29 KB |
| LICENSE | Public Domain |
| RIGHTS | PUBLIC DOMAIN |
| SOURCE | DOE OSTI |
Browse the full library · About the Tower of Babel
Full text
The opening of the work, from the library's hosted text:
U.S. Distribution Transformer Demand Phase III – Key Drivers and Managing Demand Killian McKenna, Sherin Ann Abraham, Wenbo Wang, Zephyr Zink Distribution Edge, GPAC, National Laboratory of the Rockies (NLR) June 2026 Photo from Killian McKenna, NLR Table of Contents 1 Introduction 2 Modeling Approach 3 Existing In-Service Distribution Transformer Characterization 4 Drivers of Future Growth 5 Role of Utility Practices in Transformer Demand 6 Regional Analysis of Transformer Demand 7 Industry Challenges & Demand Management Strategies National Laboratory of the Rockies | 2 Context and Challenge Over 18k downloads 2nd most downloaded NLR • Distribution transformer supply publication in delays and escalating prices remain a FY24 major industry challenge • NLR issued two reports, published in February 2024, and November 2024, widely picked up by trade journals and media outlets, thanks to Office of Electricity for funding this research • NLR has been continuing work to further refine and expand forecasts and establish how utility practices Over 13k may impact demand downloads National Laboratory of the Rockies | 3 Distribution Transformers Split-phase pole- • Distribution transformers step-down mount distribution transformer voltage for electrical service and represent the last transformation of electrical power, defined as high- Photo from Killian McKenna, NLR side voltage of <34.5 kV and rating of less than 5,000 kVA • Almost every kWh of customer energy consumption goes through a distribution transformer, and there are an estimated 60-80 million of Photo from Killian McKenna, NLR Photo from Killian McKenna, NLR them in the U.S. Split-phase pad- Three-phase pad- mount distribution mount distribution Note: Throughout this presentation, the term "transformer" refers to distribution step-down transformers. The demand for step-up transformers is also addressed in a separate transformer transformer analysis. National Laboratory of the Rockies | 4 Distribution Transformers – 500 Power & Distribution Transformer - Producer Price Index The Challenge 450 Producer Price Index (PPI 400 350 1999=100) 300 • PPA data on transformer costs 250 200 • The U.S. has seen continued 150 100 shortages for distribution 50 transformers, starting during the 0 COVID-19 pandemic Source: St. Louis Federal Reserve Bank Transformer Price Index 6 • 2025 lead times for distribution Annual Investment IOU's ($B) Distribution - Line Transformers transformers have been reported in 5 the order of months to over a year, 4 and reported average price increases 3 of 78-95% 2 1 - Source: FERC Form 1 Annual Service Transformer Investment Adjusted for GDP National Laboratory of the Rockies | 5 Our Approach – Characterizing the Stock U.S. utility landscape • There is no national inventory of distribution transformers, and distribution transformers are owned by over 3,000 utilities across the U.S., and by large commercial and industrial customers • The age and loading of the current NLR Analysis, EIA Form 861 inventory is critical to understanding future demand, in addition to load NLR estimates 60–80 million growth projections distribution transformers, with between 2.5 and 3.5 TVA of capacity National Laboratory of the Rockies | 6 Our Approach – Modeling Future Demand Initial Year • Basic overview of modeling approach: Starting Year - Raw Data Establish Initial Year Conditions Transformer Conditions Start Year ◦ Modeling new customers and increase Apply Loading in loading annually Increases ◦ Capturing transformer rating (kVA), Apply Aging loading, and installation type (pole- Energy Forecasts - Translate to Transformer Transformer Growth Rates mount, pad-mount) Raw Data Growth Apply Failure ◦ Capturing demand for each state, and Apply residential, commercial, industrial, Replacement and transportation demand New Customer Growth ◦ Separate analysis for step-up Annual transformers and data center Total Transformer Replacements & Data Demand Additions transformer demand ◦ We model unconstrained demand for Process Increment Year distribution transformers End Year National Laboratory of the Rockies | 7 Residential, Commercial, Industrial, and Transportation Data Center & Step- Utility-Owned Distribution Transformer Demand up Transformer Our Approach – The Forecasting Asset Demand for Distribution Established Thermal Aging and Calendar Demand Aging Weibull Systems Model (FC-ADDS) Failure Function Establish Initial Age Distributions Based on Building Stock Age and Failure Rates Transformer Age Distributions Start Year & Initial In- service Stock Data Center Current NLR Standard Scenarios for Load and Forecasts Generation Step-up Transformers EIA Building Stock Age Data Establish Number of Apply Loading Increases Transformers Based on Energy Consumption, Loading, and kVA Establish Transformer Peak-to- Distributions Estimate Initial Year Transformer Loading Transformer Capacity Average Ratios and Utilization Apply Calendar and Distributions and Ages Factors Thermal Aging Utility Loading Data Apply Calendar and State-Wise Total Start Year Transformer Rating Thermal Failure Function Establish Transformer Rating Number, Ratings, and Install and Loading and Install Distributions for RCI Shipment Data and Distributions Distribution for RCI Utility Transformer Transformers Assess Overloaded Distributions Transformers Apply Calendar Aging Establish State-Wise RCI New Transformer EIA Residential, Utility Transformer Replacement; Like-for- Customer Transformer Additions RCI Transformer Commercial, like, Upsizing, Splitting Calendar Aging Failure Based on Population Growth, Additions for New Sizing Practices for Industrial, and Replacement Loading Practices, kVA Customers Replacement; Consumption Upsizing, Splitting Distributions New Customer Growth Addition of New EIA Commercial and Transformer Capacity Residential Building Commercial and Establish Annual Commercial Growth Rates Industrial Load Total Replacements & and Industrial Loading Increases Growth Rates Additions Increment Year NLR Load Forecasts Increment Year Residential Load Establish Annual Residential Growth Rates (e.g., Loading Increases heat pump adoption) Start Year NLR Residential End Year Peak/Average Load for Different Load Dedicated Growth Scenarios Transformers for EV Charging Stations Database Source Data Establish Annual Port Requirements for Behind-the- Capturing: State-level, # of NLR Electric Vehicle meter for RCI and Dedicated Transformers EV Behind-the- Transformers, Installation Type, Rating Process FC-ADDS Port Forecasts & Diversity Factors meter Charging Port Additions RCI: Residential, Commercial, Industrial National Laboratory of the Rockies | 8 Key Aspects Driving Sensitivities # of Transformers Age and % Average transformer Distribution Replacements size (e.g., kVA) impacts and Average Utility Age Transformer failure the number of functions have very Size of Existing transformers, with low Distributions high impact on age Capacity of Stock Transformers average kVA increasing and Failure distributions and Diversity factors for the # of transformers Rates annual failure rates Demand EV charging and charging stations, Scenarios demand factors for Capacity of Stock Replacement Scenarios heat pumps, Low loading scenarios Run-to-fail vs. active significantly impact Utility increase capacity of Utility Decision replacement, redeployment capacity required existing stock vs. load splitting, and Transformer Making High-loading scenarios preemptive upsizing Loading decrease capacity of Process anticipating growth vs. high existing stock utilization have significant impacts on demand required NLR | 9 Characterizing the Existing Stock – Pole-Mount Transformers and Lower Sizes Dominate Number of Deployed Assets • We are capturing the distribution in transformer rating, and installation type, through a combination of shipment data and utility datasets ◦ The majority of transformer installations are pole-mounted and ratings < 100 kVA ◦ The majority of transformer capacity is pad-mounted and ratings >100 kVA National Laboratory of the Rockies | 10 Characterizing the Existing Stock – A Significant Portion of Assets Are Beyond Expected Lifetimes • Utility reporting shows aging infrastructure at or exceeding life expectations. Through modeling the age of the building stock and transformer failure rates we estimate that: ◦ 17.5 million distribution transformers are beyond their expected designed life DTE Electric Asset Age Analysis Utilities normally assume