Final Technical Report (FTR) Cover Page a.​ Federal Agency Department of Energy b.​ Award Number DE-EE0010723 Novel PV Array System Design to Accelerate Solar Deployment, Reduce LCOE, Reduce Land Use c.​ Project Title Competition, and Increase Siting Flexibility d.​ Recipient Organization Planted Solar, Inc. e.​ Project Period Start: 8/1/2023 End: 7/31/2025 Richard Erb f.​ Principal Investigator (PI) VP Product Eric Brown g.​ Business Contact (BC) CEO h.​ Certifying Official (if different from the PI or BC) N/A Signature​of Certifying Official​ ​ ​ ​ ​ Date By signing this report, I certify to the best of my knowledge and belief that the report is true, complete, and accurate. I am aware that any false, fictitious, or fraudulent information, misrepresentations, half-truths, or the omission of any material fact, may subject me to criminal, civil or administrative penalties for fraud, false statements, false claims or otherwise. (U.S. Code Title 18, Section 1001, Section 287 and Title 31, Sections 3729-3730). I further understand and agree that the information contained in this report are material to Federal agency’s funding decisions and I have any ongoing responsibility to promptly update the report within the time frames stated in the terms and conditions of the above referenced Award, to ensure that my responses remain accurate and complete. Page 1 of 39 Table of Contents: Executive Summary: Motivation and Importance Project Goals and Objectives Major Accomplishments Public Benefit Background Project Objectives: Public Benefit Project Results and Discussion: Q3 2023 Reporting Period Q4 2023 Reporting Period Q1 2024 Reporting Period Q2 2024 Reporting Period: Q3 2024 Reporting Period Q4 2024 Reporting Period Q1 2025 Reporting Period Q2 2025 Reporting Period Q3 2025 Reporting Period Summary of Planned vs Actual Milestone Deliveries Significant Accomplishments and Conclusions: Highlight any significant accomplishments and explain why they are significant. Both positive and negative outcomes should be included. Describe any challenges encountered under this award and the lessons learned. If applicable, describe why pivots or reduction in scope occurred. Path Forward Products: Project Team and Roles References: Page 2 of 39 Acknowledgement: This material is based upon work supported by the U.S. Department of Energy's Office of Energy Efficiency and Renewable Energy (EERE) Solar Energy Technologies Office (SETO) under the Award Number DE-EE0010723. Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof. Executive Summary Motivation and Importance The increasing demand for solar energy faces significant barriers, including inefficient construction processes, high project costs limiting LCOE reductions, and diminishing availability of "good" sites with favorable interconnection. Conventional solar installations are often constrained by long construction timelines and the need for flat, large plots. Furthermore, the industry struggles with a shortage of skilled labor. Planted Solar aims to address these challenges by fundamentally transforming solar deployment from a construction project into a streamlined manufacturing process. Our novel approach combines high-density racking, integrated terrain-following design software, and installation automation. Unlike competing solutions that either assist with standard array assembly or offer dense packing without terrain adaptability or automation, Planted's technology uniquely brings together a new array product with in-place automated manufacturing to achieve the lowest possible cost, greater site flexibility, and accelerated deployment. Project Goals and Objectives In the scope of this project, Planted Solar will integrate additional technology elements that are necessary to implement the company’s existing array design effectively on sloped/undulating sites, small/irregular sites, and sites with significant sub-surface risks (such as brownfield sites with contaminated soil or shallow rocks). Planted Solar will validate these technical advances on full-scale arrays that exhibit some of these characteristics. End of project goals include bankability assessments for these pilot systems, firm orders for further systems with similar characteristics, and techno-economic analyses addressing this segment of the PV market. Page 3 of 39 Major Accomplishments Throughout the project, Planted Solar achieved significant milestones, demonstrating the technical effectiveness and economic feasibility of its methods: Phase 1: Foundations and Initial Validation (Q3 2023 - Q2 2024) ●​ Program Management & Integration Efforts: Established a robust quality management plan and Gantt chart. Focused on structural build capabilities, including extensive soil capacity testing for foundation angles and features crucial for higher loads and weaker soils. ●​ Installation Machine Advancement: Enabled use on steeper slopes and improving post-driving control. ●​ Software Enhancements: Integrated a new layout tool for faster, more flexible layouts on irregular plots and developed a digital surface model (DSM) slope analysis tool to accelerate site evaluation. ●​ Competitive Analysis & LCOE Parameters: Identified and analyzed leading competitive PV array designs and defined all key parameters for LCOE assessments, forming the basis for cost comparisons. ●​ Go/No-Go Milestones Achieved (Q2 2024): ○​ GNG-A (Post Placement Accuracy): Achieved ≥99% yield of accurate post placements on sloped/undulating terrain (200+ posts), verified by on-board instrumentation and surveying, proving automated assembly efficiency. ○​ GNG-B (Module Attachment Yield): Achieved ≥99% yield of acceptable module attachments on demonstration arrays (200+ modules), validating readiness for deployment. ○​ GNG-C (Layout Completion Time): Demonstrated automated layout creation in less than 5 minutes for small/irregular sub-plots, with comparable area utilization to manual engineer design, proving significant time and cost savings. ○​ GNG-D (Customer Contracts): Secured signed contracts for pilot arrays on sloped and small sub-plot sites, indicating strong customer engagement. ○​ GNG-E (LCOE Advantage): Preliminary techno-economic report showed >10% LCOE advantage for Planted technology on pilot projects compared to traditional providers, highlighting economic feasibility. Phase 2: Commercialization and Demonstration (Q3 2024 - Present) ●​ Bankability & Certification: Completed UL2703 certification for the array technology, a critical step for meeting industry standards and a keystone for bankability review. Contracted with DNV Energy for a comprehensive bankability report. ●​ Demo System Design & Permitting: Designed demo systems for both sloped/undulating sites and small sub-plots, submitting layouts to developers. Initiated permitting Page 4 of 39 processes for the demonstration sites, with EPA and electrical permits approved and zoning pending. ●​ Installer Machine and Array Refinements: Implemented learnings from GNG demos into improved post installer machines and array product designs. Performed extensive small-scale demonstrations and reliability testing across various soil and slope types, informing operations and logistics. ●​ Operations & Maintenance (O&M) Improvements: Rigorously updated O&M procedures, including module maintenance and installation guidelines, and completed compatibility testing with major module manufacturers, further improving bankability. Public Benefit The project contributed to solar capacity expansion and national energy goals by enabling greater energy generation per acre of land (2X more), allowing larger projects on existing sites or requiring less land for target capacities. It opens up solar development on highly undulating terrain without costly grading, making previously impractical or uneconomical sites viable. This shifts solar projects to non-prime land, reducing competition with agriculture or other high-value uses and making site identification easier. The design also allows for sheep grazing under the arrays, supporting land dual-use and vegetation management. Ultimately, Planted's advancements mitigate technical risks, reduce LCOE, and increase siting flexibility, accelerating the deployment of abundant and affordable clean energy. Page 5 of 39 Background A handful of factors have become critical barriers to beneficial deployments of solar projects. First, installing conventional solar arrays entails construction projects which are massively inefficient compared to other factory-streamlined processes. Long construction timelines and high project costs inhibit further substantial reductions in LCOE, which ultimately determines the incentive to deploy. Site availability, particularly sites with good interconnection, has also become rare as more and more “good” sites have been built: Analysis from Paces shows trends of sites across the United States (“Suitable sites” = parcels with +1 MW of feeder capacity and +15 buildable acres.) Page 6 of 39 Racking and installation methods that accommodate the high variation in site conditions are needed. Skilled labor has also become harder and harder to find. With this project, Planted aims to reduce these barriers by developing high-density racking, integrated terrain-following design software, and installation automation that makes it more flexible, easier, and faster to install solar projects. While others are beginning to apply automation to installing solar fields, they are focusing on techniques that assist with assembly of standard arrays, but do not fundamentally transform them from construction projects into a true mass-manufacturing analog. Other densely-packed, low-profile array designs may appear similar to our approach, but rely on manual assembly in the field, and cannot follow uneven terrain. Planted’s technology uniquely combines a novel Page 7 of 39 array design with an automated in-place manufacturing approach. The synergy between these two innovations is essential to achieving the lowest possible cost. No system other than Planted’s offers that combination of performance: e.g. the few that offer high energy density and good utilization of irregularly-shaped plots require flat land and are more expensive; the one that offers comparable slope/undulation tolerance in other respects is like a standard SAT but even more expensive; and the competing options with lowest LCOE are not the most flexible ones. Project Objectives: Specific objectives per the Statement of Project Objectives were: 1.0 - Develop/demonstrate technology needed to install on undulating/sloped terrain and land with sub-surface risks: Planted Solar’s existing, demonstrated array design already allows connections to articulate so the array can conform to sloped/undulating topography. To take advantage of this capability and efficiently and successfully install an array on a sloped/undulating site, we need to be able to quickly and accurately map terrain, vary the prescribed post depth from post to post so the array properly conforms to the terrain and satisfies articulation and no-self-shading constraints, and enable the installation robot to adapt dynamically during installation to account for deviations between the topographic map and ground truth. Task 5.0 continued this effort in the second budget period. 2.0 - Develop/demonstrate technology needed to install on small/irregular plots: The small unit cell size in Planted Solar’s existing, demonstrated array design in principle enables high coverage of small/irregular parcels (unlike conventional technologies constrained by the need to orient modules in long rows). To take advantage of this capability, the array layout software must be able to automatically design arrays, with minimal supervision by engineers, that conform to a variety of additional constraints. Task 6.0 continued this effort in the second budget period. 3.0 - Complete techno-economic analyses: Planted Solar will develop detailed cost, performance, and technology impact models that address varied scenarios, including varied combinations of factors such as geographical location, climate, soil conditions, slope, undulations, plot size/shape, module type and performance, input unit costs, O&M, financial parameters, energy storage, and other site-specific details. We will assess the impact of these factors on capital cost and LCOE and compare the results with alternative conventional and emerging technologies. As part of this Task we will identify and analyze the leading competitive array designs, and also recruit solar project developers with proven track records of early technology adoption to join an informal “early stage product council” to receive briefings on Planted’s technology, demonstrate customer engagement, and offer voice-of-customer input. Page 8 of 39 Task 4.0 was removed as a result of executive order. Tasks 5.0 and 6.0 continued tasks 1.0 and 2.0 into the second budget period. 7.0 - Complete techno-economic analyses: Continuation of Task 3 from Budget Period 1. We will increase the sophistication of the models and the number and variety of the case studies considered. We will also validate successful technology transfer by demonstrating firm orders for additional systems on sites with characteristics similar to those in Tasks 5 and 6. Project milestones to quantify the above objectives were: ●​ GNG-A: Yield of accurate post placements ○​ Success Value: ≥ 99% ●​ GNG-B: Yield of acceptable module attachments ○​ Success Value: ≥ 99% ●​ GNG-C: Completion time to create a layout with area utilization comparable to manual design by an engineer ○​ Success Value: 5 minutes ●​ GNG-D: Signed contracts with customers who will build two pilot arrays: one project on a site that is a sloped site or a sloped/ undulating site and one project on a site that contains small sub-plots (*) ○​ Success Value: One array in each site category ●​ GNG-E: Projected LCOE advantage vs. standard PV technology ○​ Success Value: > 10% ●​ Milestone EOP-A Tech: Yield of post placements on sloped demo system ○​ Success Value: ≥ 99% ●​ Milestone EOP-B Tech: Area coverage ○​ Success Value: ≥ 70% ●​ Milestone EOP-C Costs: Projected LCOE advantage vs. standard (manual, non-automated PV BOS technology) ○​ Success Value: > 20% ●​ Milestone EOP-D Stakeholder: Firm orders ○​ Success Value: ≥ 10 MW-DC Public Benefit The project contributed to solar capacity expansion and national energy goals and benefit U.S. electricity customers by lowering energy costs, expanding the nation’s ability to deploy solar generation (thereby reducing air emissions), and enhancing grid resiliency. Cost savings. Over the next two decades, the U.S. will need very large additions of utility-scale and distributed solar to decarbonize electricity—multiple credible pathways envision solar Page 9 of 39 providing ~40% [ref 1] or more of U.S. electricity by mid-century. In that context, assume a “business-as-usual” baseline built with conventional single-axis-tracking (SAT) PV. Now suppose 20 GW of that buildout instead uses Planted arrays—a high but plausible target—corresponding to ~40 TWh/year of generation. If Planted reduces levelized cost of energy (LCOE) by ~25%, total savings to customers would be ≥ $500 million/year at a $50/MWh baseline. Actual savings would likely be higher because siting flexibility (higher density; use of irregular, sloped/undulating, or brownfield plots) allows projects to locate nearer load and existing interconnections, reducing the need for long-distance transmission. While location-specific, national studies suggest transmission can add a material premium to delivered energy costs (often on the order of several percent up to a third of plant-level LCOE), so avoided transmission buildout can be comparable to generation-side savings. A reasonable first estimate for customer savings is on the order of ~$1 billion per year. Solar capacity and siting. Identifying and permitting sites for both distributed and utility-scale solar has become more challenging nationwide due to local land-use concerns, habitat and agricultural impacts, and transmission interconnection backlogs. Planted addresses these constraints by (1) cutting land needs by more than half (vs. a conventional system producing the same energy) and (2) expanding the envelope of cost-effective sites to include highly sloped or undulating terrain, irregular boundaries, and land with sub-surface risks or on brownfields. Under these constraints, the “last” tens of gigawatts of otherwise planned solar may be delayed or not built in some regions without technologies like Planted that unlock more sites and denser layouts—mitigating the need for long new transmission corridors. Planted’s system generates approximately 570 MWh/acre/year, compared to 280 MWh/acre/year for conventional single-axis tracker (SAT) systems—a 2–3x increase in energy generation per acre. This translates to a land savings of over 50% for a project targeting the same annual energy yield. For example, a 10 MWDC SAT system that generates ~14 GWh/year typically requires ~50 acres; a Planted system generating the same energy would require ~25 acres. Beyond raw density, Planted’s array allows effective development on irregular, sloped, and undulating terrain without grading or trenching, thereby expanding siting options to land previously considered unsuitable—including brownfields, non-contiguous parcels, and terrain with up to 30% grade or 5°/m undulation (vs. 15% and ~2°/m for typical SAT systems). Distributed generation and grid resiliency. Distributed generation (including behind-the-meter, community-choice/aggregation programs where applicable, and community solar) improves resiliency by placing generation near consumption, easing peak-time transmission stress and enabling local service during transmission outages. Site size and shape often limit these projects; Planted’s ability to approximately double site energy output and conform to irregular or noncontiguous parcels increases the amount of distributed generation that can be built cost-effectively. The value to customers is difficult to quantify precisely and depends on local tariffs and avoided-cost structures, but an order-of-magnitude estimate of ~$100 million/year Page 10 of 39 (e.g., ~$20/MWh across ~5 TWh/year enabled or unlocked) is reasonable, with upside as soft-cost reductions and interconnection reforms take effect. Project Results and Discussion: Q3 2023 Reporting Period Planned Milestones vs Accomplishments: All milestones delivered on time. Milestone 1.0.1: Quality management plan: Gantt chart with buffers, QA/QC Success Value: Quality management plan that accurately describes processes and systems that define and control production to meet minimum acceptance standard Assessment Tool / Method of Measuring success value: ISO standards or equivalent Verification Process: Quality management plan submitted to DOE Metric justification, additional notes: A quality management plan based on a Project Lifecycle Management approach with projects partitioned into distinct phases separated by key decision points (Preliminary Design Review (PDR), Critical Design Review (CDR), and System Integration Review (SIR), to clearly communicate tasks, responsibilities with deadlines, assess/mitigate foreseen risks, and establish standards for gauging performance. Buffer chart to be reviewed with DOE on a monthly basis. Results: Quality Management Plan and Gantt chart were delivered on time. Page 11 of 39 Milestone 1.3.1: Leading competitive conventional PV array designs (*) identified Success Value: 5 Assessment Tool / Method of Measuring Success Value: See definition at end of table Verification Process: List of specific technologies chosen and rationale for each submitted to DOE Metric Justification, Additional Notes: Baseline cases for MS1.3.2, GNG-E, EOP-C will be drawn from this list Results: 5/5 leading competitive convention PV array designs were delivered on time. The basis of selection included market share, US focus, and product similarity. Summary of quarterly progress: The initial reporting period for Q3-2023 was focused on setting up the correct program management structure and laying the foundation for remaining projects along with ongoing improvement efforts focused on Task 1.0 and Task 2.0, in addition to the specific deliverables noted above. Planted’s hardware team made improvements to the array structural design by undertaking a wider range of soil capacity testing to validate different foundation angles and design features that are critical to expanding the reach of simple, high-density arrays into areas of higher loads (snow, wind) and weaker soils. Additionally, design improvements of the installation machine enabled the use of the machine on steeper slopes. The team also improved our post-driving control strategy in that same range of soil types. Page 12 of 39 The planning software that enables site design for undulating/sloped terrain and small sub plots saw significant improvement in Q3-2023. A new layout tool was introduced allowing for faster and more flexible layouts on irregular plots. This allows Planted to quickly develop plans for undulating/sloped terrains in harsher climates, greatly expanding the regions in which the product can make an impact. Q4 2023 Reporting Period Planned Milestones vs Accomplishments: All milestones delivered on time. Milestone 1.2.1: Site examples containing small sub-plots identified Success Value: 10 Assessment Tool / Method of Measuring Success Value: Examples of plots with small sub-plots being considered for solar projects by solar developers identified for use in GNG-C. System size will be ≥ 500 kW. Verification Process: GPS coordinates of sites submitted to DOE. High level summary of voice-of-customer notes pertaining to these sites also submitted to DOE. Metric Justification, Additional Notes: Sites will be compiled from engagement with system developers (our customers) who are interested in these types of sites and who are providing market guidance on key features of these sites. This list provides examples for testing in MS1.2.5 and GNG-C and provides likely (though not required) candidates for MS1.2.6. Results: Planted delivered the GPS coordinates and Voice-of-Customer notes for 10/10 sites ≥ 500 kW on time. Size in MWp ranged from 0.65 to 204. Milestone 1.2.2: QA metrics for topographic data Assessment Tool / Method of Measuring Success Value: These metrics define whether software fusion of topographic data layers is successful. Verification Process: QA metrics definitions submitted to DOE. Metric Justification, Additional Notes: Needed to define testing procedure and pass/fail criteria for MS1.1.1 Results: Planted delivered QA metrics for topographic data on time, including the limits and rationale. Criteria were: data format, resolution of surface data, regularity of surface data, data smoothness, data slope, and recency of data Milestone 1.2.3: QA metrics for array layout software Assessment Tool / Method of Measuring Success Value: These metrics define whether the array layout software is operating correctly Verification Process: QA metrics definitions submitted to DOE. Metric Justification, Additional Notes: Needed to define testing procedure and pass/fail criteria for MS1.2.5 Page 13 of 39 Results: Planted delivered QA metrics for array layouts on time, including values and rationale. Criteria included no software-generated error, all posts placed within boundary, module tilts within the prescribed bounds, number of rows and columns matching user inputs, and others. Milestone 1.1.1: Examples of topographic data fusion passing QA metrics Success Value: ≥ 5 Assessment Tool / Method of Measuring Success Value: Number of distinct examples of topographic data fusion passing QA metrics defined in MS1.2.2 Verification Process: Report sent to DOE with summary of testing Metric Justification, Additional Notes: While 1 topo layer suffices to enable layout for nearly flat plots, fusion of 2 layers will typically be needed for highly sloped and/or undulating terrain Results: Planted delivered 5/5 topographic data fusion examples on time. Publicly sourced LIDAR data was used for fusions into a single Digital Elevation Map for 5 sites, each of which was validated against criteria on data format, resolution of surface data, regularity of surface data, data smoothness, data slope, and recency of data. Milestone 1.3.2: Leading competitive conventional PV array designs analyzed Success Value: 3 Assessment Tool / Method of Measuring Success Value: Subset of leading competitive conventional PV array designs analyzed in detail and incorporated into Planted’s LCOE model to facilitate comparison with Planted’s technology across diverse solar project scenarios Verification Process: Summary of competitive analysis submitted to DOE Metric Justification, Additional Notes: This analysis will provide the basis for the LCOE comparison in GNG-E and EOP-C. (Limited to the top 3 initially for tractability.) Results: Planted delivered the analysis on time for 3/3 competitive designs. Page 14 of 39 This quarter, Planted made significant progress on our array layout software and next-generation installation machine. We released a new array packing mechanism which makes the software more competitive with a man-made site layout. We also performed significant work on measuring terrain, which enables our software to provide the installation machine with a high-accuracy layout that follows the curves of the ground. We also completed the integration of a digital surface model (DSM) slope analysis tool in design software which is key to accelerating the evaluation of viable project sites and enabling detailed design based on topographic information. With respect to the installation machine, we completed the majority of the design improvement work and pre-manufacturing testing. After gaining confidence in our latest hardware, we released drawings for the major assemblies and purchased small parts. We also performed testing demonstrating that a new locating method for the machine greatly improves post placement accuracy, while simultaneously proving through further testing that the latest array design is more tolerant to position error than the previous generation. These increased accuracy capabilities support GNG-A and GNG-B. Q1 2024 Reporting Period Planned Milestones vs Accomplishments: All milestones delivered on time. Milestone 1.1.2: Identification of project site(s) intended for pilot project: a sloped site or a sloped/ undulating site (*) Success Value: At least one site Assessment Tool / Method of Measuring Success Value: Count of suitable sites (defined below table) identified by partners (independent solar project developer(s), contractor(s), or owner-user(s)). System size will be ≥ 500 kW. Verification Process: Descriptions, boundary maps, and GPS coordinates of sites submitted to DOE Metric Justification, Additional Notes: Identification of sites demonstrates progress toward securing contracts, necessary for GNG-D. The most likely partner has already been identified in the proposal (see letters of support). However, Planted is in discussions with multiple potential partners and customers, and a different partner could be selected for pilot projects. Results: Planted delivered 1/1 potential pilot site on time, a 7.75MWp site in a higher density exurban area. Milestone 1.1.3: QA metrics for array mechanical parameters Assessment Tool / Method of Measuring Success Value: These metrics define whether an arrays complies with the mechanical engineering specifications Verification Process: QA metrics definitions submitted to DOE. Metric Justification, Additional Notes: Needed to define measurement procedure and pass/fail criteria for MS1.1.4 and GNG-A Page 15 of 39 Results: Planted delivery QA metrics for array mechanical parameters on time, including the description and rationale. Metrics were primarily set on geometrical goodness as well as fitment and visual acceptability. Milestone 1.2.5: Tests conducted to demonstrate correct operation of array layout software for small sub-plots Success Value: 10 Assessment Tool / Method of Measuring Success Value: Software for layout of arrays conforms to QA metrics (defined in MS1.2.3) when tested on all 10 site examples identified in MS 1.2.1 Verification Process: Report sent to DOE with summary of testing Metric Justification, Additional Notes: At this stage, the output of the software is “correct” (conforms to QA requirements) but not necessarily “optimized” (i.e. comparable to performance of human engineer). Results: Planted delivered the results of 10/10 layout software operation tests on time. Page 16 of 39 Milestone 1.2.6: Identification of project site(s) intended for pilot projects: a site containing small sub-plots (*) Success Value: At least one site Assessment Tool / Method of Measuring Success Value: Count of suitable sites (defined below table) identified by partners (independent solar project developer(s), contractor(s), or owner-user(s)). System size will be ≥ 500 kW. Verification Process: Descriptions, boundary maps, and GPS coordinates of sites submitted to DOE Page 17 of 39 Metric Justification, Additional Notes: Identification of sites demonstrates progress toward securing contracts, necessary for GNG-D. The most likely partner has already been identified in the proposal (see letters of support). However, Planted is in discussions with multiple potential partners and customers, and a different partner could be selected for pilot projects. Results: Planted delivered a potential pilot site on time, a 7.75MWp site in a higher density exurban area. Milestone 1.1.4: Simulated examples showing that topographic mapping and array planning capabilities result in arrays that pass the QA metrics defined in MS 1.1.3 Success Value: 5 Assessment Tool / Method of Measuring Success Value: Count of simulated examples with varied topographies (from MS1.1.1), in which the simulated array output conforms to QA metrics. In the simulations, random discrepancies in GPS sensor values, mapped altitude values, and post placement positions will be introduced (matching the observed variance distributions for these parameters). The software will adapt the design on the fly as it would in the field. The simulated array output will be checked against the QA criteria. Verification Process: Report sent to DOE with summary of simulated testing Metric Justification, Additional Notes: This milestone is essentially a simulation of the empirical test to be conducted in GNG-A to establish confidence that it will be passed. The overall idea is to show that the planning software adapts as needed to uncertainties in position information and imperfections in post placement to keep all angles and distances within mechanical design tolerances. Results: Planted delivered 5/5 simulation examples on time. Milestone 1.2.4: Control test for software performance Assessment Tool / Method of Measuring Success Value: Testing protocol specification to compare performance of automated software layout vs. layout by human engineer Verification Process: Protocol submitted to DOE Metric Justification, Additional Notes: Needed for GNG-C Results: Test protocol was delivered to the DOE on time, including definitions, methodology for preparation and test, and success criteria based on area utilization and design time. Page 18 of 39 In the Q1-2024 reporting period, Planted completed the build and bring-up of our next generation installation machine and demonstrated functionality of the subsystems. We also demonstrated good data flow between the layout software and robot, both in online and offline mode. The bring-up of these capabilities ensures the machine can take a site plan from the layout software and accurately install it on sloped/undulating terrain or on small subplots. Planted also finalized an initial demonstration build on flat terrain. The demonstration build proved the array is capable of being easily installed on posts with real-world conditions. This was a significant risk buy down for future builds on sites with sloped/undulating terrain. Page 19 of 39 ↓ Page 20 of 39 Q2 2024 Reporting Period: Planned Milestones vs Accomplishments: All milestones delivered on time, including the Budget Period 1 Go/No-Go milestones. Milestone 1.3.3: All key parameters for LCOE assessments Assessment Tool / Method of Measuring Success Value: All key parameters needed for LCOE assessments will be defined, justified, and agreed with DOE Verification Process: Document with parameters submitted to DOE Metric Justification, Additional Notes: Parameters will include but are not limited to financial parameters, price assumptions, geographic locations, and O&M parameters (e.g., soiling, inspection, replacements, etc.). To be used for the LCOE assessments in GNG-E and EOP-C Results: Planted delivered all key parameters for LCOE assessments on time including basis values for: Modules Cost, Inverter Cost, eBOS Cost, sBOS Cost, Installation Cost, Site Prep Cost, EPC Overhead, Sales Tax, Permitting & Engineering Cost, Interconnection & Transmission Cost, Contingency margin, Developer Overhead, Developer Profit, Project Size, DC:AC Ratio, Production, Land Use, Labor Rate, O&M Costs, Discount Rate and System Useful Life. Milestone 1.3.4: Members recruited to informal “early stage product council” Success Value: ≥ 3 Assessment Tool / Method of Measuring Success Value: The ”early stage product council” will be comprised of influential developers with proven track records of early technology adoption who will receive briefings on Planted’s technology and progress and will provide recommendations to improve the go-to-market strategy Verification Process: List of participants and summary of recommendations to submitted to DOE Metric Justification, Additional Notes: Formalizes role of voice of customer input Results: Planted recruited 3/3 participants to an early stage product council and delivered a summary of their feedback on time. GNG-A: Yield of accurate post placements Success Value: ≥ 99% Assessment Tool / Method of Measuring Success Value: Fraction of posts installed at the local test site (on sloped/ undulating terrain) that conform to the array’s mechanical design tolerance as specified in QA metrics from MS 1.1.3 (i.e. do not require re-work due to positioning error). The test will include at least 200 posts in total (divided into two or more sessions). Verification Process: Data plot of empirical test results with statistical analysis sent to DOE Metric Justification, Additional Notes: This level of accuracy ensures that automated assembly can proceed efficiently in the field while module articulation remains within the design specifications. Results: Planted built a demonstration array that met the criteria of 200 posts on high slope and verified the post placements using a combination of post installer machine on-board Page 21 of 39 instrumentation and traditional surveying equipment. Post positions were validated against all metrics in milestone 1.1.3 with a >99% success rate. GNG-B: Yield of acceptable module attachments Success Value: ≥ 99% Assessment Tool / Method of Measuring Success Value: Fraction of modules attached in full compliance with QA metrics from MS 1.1.3 in a setting outside of the Incubator project scope (e.g., a system built for a paying customer), for at least 200 modules. Verification Process: Data plot of empirical test results with statistical analysis sent to DOE Metric Justification, Additional Notes: Module placement is not part of R&D within the Incubator project scope because the special terrains on which the Incubator project focuses do not pose special challenges on module placement accuracy. However, this GNG is included because it is necessary to verify readiness to proceed to Budget Period 2, along with GNG-A Results: Planted built three demonstration arrays to meet the criteria of 200 modules and verified the module placements using a combination of post installer machine on-board instrumentation and traditional surveying equipment. Module positions were validated against all metrics in milestone 1.1.3. GNG-C: Completion time to create a layout with area utilization comparable to manual design by an engineer Success Value: 5 minutes Assessment Tool / Method of Measuring Success Value: Average over ten distinct design examples of time for the automated design software to complete mechanical and electrical layout for a small/irregular sub-plot with arbitrary boundaries, with comparable or better area utilization than manual design by an engineer. (“Comparable” means the module coverage ratio for the sub-plot layout designed by the software is within 10% of the manual design value, completed separately by a human as part of testing in parallel.) Verification Process: Report sent to DOE with design summaries and run logs Page 22 of 39 Metric Justification, Additional Notes: A large system might comprise multiple sub-plots, so performance needs to be fast. In comparison, an engineer might need several hours to optimize the design for each sub-plot. Testing protocol defined in MS 1.2.C. Results: Planted performed timed automated layouts of ten sites demonstrating that utilization of Planted’s software enabled layouts to be created in less than 5 minutes with area utilization comparable to that which would be accomplished manually by a design engineer. GNG-D: Signed contracts with customers who will build two pilot arrays: one project on a site that is a sloped site or a sloped/ undulating site and one project on a site that contains small sub-plots (*) Success Value: One array in each site category Assessment Tool / Method of Measuring Success Value: Count of contracts signed with independent solar project developer(s), contractor(s), or owner-user(s) to build pilot arrays . System size will be ≥ 500 kW. Verification Process: Redacted contracts sent to DOE—information to be retained in DOE submission to include: name of customer, location of site, size of PV array, target completion date, termination clauses Metric Justification, Additional Notes: The pilot arrays will meet the requirements needed for Tasks 5 and 6 in Budget Period 2. Results: Planted delivered a signed contract with a customer on time for 2/2 pilot sites. GNG-E: Projected LCOE advantage vs. standard PV technology Success Value: > 10% Assessment Tool / Method of Measuring Success Value: Projected relative size of LCOE advantage for the two projects associated with GNG-C (compared with the best commercially available alternative array design). Verification Process: Preliminary techno-economic report delivered to DOE Page 23 of 39 Metric Justification, Additional Notes: Clear cost advantage of the technology will be essential to drive commercial adoption. Results: Planted delivered the preliminary techno-economic report on time, which demonstrated that the two projects associated with GNG-C have an LCOE cost advantage using Planted technology vs traditional providers >10%. During the Q2-2024 reporting period, Planted performed research and development in support of the BP1 Go-No-Go milestones. Planted made significant advancements towards the project goals of implementing the company’s existing array design effectively on sloped/undulating sites, small/irregular sites and sites with significant sub-surface risks. In April, Planted completed a large-scale demonstration build that verified the end-to-end construction process was effective on sloped and undulating terrain in support of GNG-A and B. The demonstration site layout was completed using Planted’s layout software, which was also used to analyze the site slope and undulate the array to conform to the sloped terrain. This build was the first demonstration of the installation machine’s performance on high slopes and undulating terrain. We verified that machine handleability on slopes was sufficiently easy and that there were not marked increases to installation time on slopes compared to flat terrain. Following installation, data review from both machine data and from manually gathered verification data showed that post installation accuracy met design targets for GNG-A and GNG-B. Furthermore, the demonstration build verified the ergonomics and speed of module installation on sloped terrain. This provided new learnings about design improvements for the wheeled cart used to operate underneath the modules, but ultimately, no notable differences were observed in the overall time to completion between installation on slopes and installation on the preceding flat terrain builds. Page 24 of 39 Page 25 of 39 Q3 2024 Reporting Period Planned Milestones vs Accomplishments: Due to the project pause while the DOE reviewed the continuation application, the milestone schedule was updated to move all milestone due dates back by two months. Therefore, no milestones were due in Q3 2024. During the Q3 reporting period, Planted made significant progress toward securing a bankability report for task 7.0. Planted completed UL2703 certification of our array technology, a critical step in meeting industry standards for array hardware. This certification ensures Planted’s technology is mechanically and electrically reliable as verified by the certification body. The certification is a keystone of bankability review. Developmental structural tests and analysis contributed to the reliability review to be performed by the bankability reviewers. Planted contracted with a firm to provide the bankability report and is actively working through the review process. Planted also continued to progress toward successful completion of the demo systems of EOP-A and EOP-B. Learnings from the previous GNG demos were implemented on both the post installer machine and the array product. Planted continued development work toward building our small/irregular demo site, including iterating on site layouts, coordinating with the customer, and performing site visits. Page 26 of 39 Q4 2024 Reporting Period Planned Milestones vs Accomplishments: All milestones delivered on time. Milestone 2.5.1: Demo system designed for a sloped site or a sloped/undulating site (*) Assessment Tool / Method of Measuring Success Value: Designs for pilot systems (cf. GNG-D) have been submitted to independent developer(s). Verification Process: Copies of design submission communications delivered to DOE. Metric Justification, Additional Notes: The pilot array will be needed for Subtask 5.2. Results: Planted submitted the demo system layout to the developer and delivered records of the communication on time. Milestone 2.6.1: Demo system designed for a site containing small sub-plots (*) Assessment Tool / Method of Measuring Success Value: Designs for pilot systems (cf. GNG-D) have been submitted to independent developer(s). Verification Process: Copies of design submission communications delivered to DOE. Metric Justification, Additional Notes: The pilot arrays will be needed for Subtask 6.2. Note: design will show that the demo system will satisfy EOP-B. Results: Planted submitted the demo system layout to the developer and delivered records of the communication on time. During the Q4 reporting period, Planted made continued progress toward securing a bankability report for task 7.0 with additional documentation submission and review by the party Planted has contracted to complete the bankability report. In addition, Planted performed further certification activities for additional designs which will improve Planted’s bankability. Planted also continues progress toward successful completion of the demo systems of EOP-A and EOP-B. Throughout Q4, Planted performed many small scale demonstrations of our technology, including testing of the post installer at locations around the country of various soil and slope types. Additionally, Planted did further development on our foundation structures, which were tested during those same demonstrations. The demonstrations informed our operations and logistics with respect to equipment transit, communication, on-site amenities, material handling, and other areas. Planted also worked closely with the demo site customer on finalizing the site build designs and plans towards permit submission, including completion of task 2.5.1 and 2.6.1 with a site layout design for our pilot site. We also continued development work toward building our demo site through coordinating with the customer and performing site visits. Page 27 of 39 Q1 2025 Reporting Period Planned Milestones vs Accomplishments Of the Planned vs Actual Activities, while Planted submitted for permits in time, delays by external entities led to the incomplete task 2.5.2 and 2.6.2, and as of end of the quarter. Milestone 2.5.2: All permits needed for construction of first demo system issued by AHJ Success Value: Permits issued Assessment Tool / Method of Measuring Success Value: Permits issued Verification Process: Copies of permits submitted to DOE Metric Justification, Additional Notes: The pilot arrays will be needed for Subtask 5.2. Results: Planted submitted permits for the demonstration system to the pilot site AHJ. Permits were acknowledged and are under review by the pilot site AHJ. Receipt of the permit is now waiting on the city. Milestone 2.6.2: All permits needed for construction of second demo system issued by AHJ Success Value: Permits issued Assessment Tool / Method of Measuring Success Value: Permits issued Verification Process: Copies of permits submitted to DOE Metric Justification, Additional Notes: The pilot arrays will be needed for Subtask 6.2. Results: Planted submitted permits for the demonstration system to the pilot site AHJ. Permits were acknowledged and are under review by the pilot site AHJ. Receipt of the permit is now waiting on the city. During the Q1 reporting period, Planted made continued progress towards a successful demonstration project. We performed significant reliability testing and updates on the post installer machines including updates to mechanism design and software for tracking the reliability and performance of the machine during the build. Furthermore, all five installer machines went through the commissioning process to verify they are ready for the demonstration project. Toward improving bankability, we also made rigorous updates to our operations and maintenance procedures. This included better handling for module maintenance and installation design guidelines. We also worked through compatibility testing with important module manufacturers, which positively impacts bankability as well as customer engagement. Page 28 of 39 Developed all-weather installation cart for easy install and maintenance Q2 2025 Reporting Period Planned Milestones vs Accomplishments Of the Planned vs Actual Activities, while Planted submitted for permits in time, delays by external entities led to the incomplete task 2.5.2, 2.5.3, 2.6.2, and 2.6.3 as of the end of the quarter. Milestone 2.5.3: Demo systems completed for a sloped site or a sloped/undulating site (*) Assessment Tool / Method of Measuring Success Value: Pilot system (cf. GNG-D) has been completed and passed AHJ inspection Verification Process: Statement from EPC delivered to DOE, including yield assessments Metric Justification, Additional Notes: The pilot array will be needed for Subtask 5.2. Results: Planted submitted permits for the demonstration system to the pilot site AHJ. Permits were acknowledged and are under review by the pilot site AHJ. Receipt of the permit is now waiting on the city. Demo system build is contingent on permits. Milestone 2.6.3: Demo system completed for a site containing small sub-plots (*) Assessment Tool / Method of Measuring Success Value: Pilot system (cf. GNG-D) has been completed and passed AHJ inspection Verification Process: Statement from EPC delivered to DOE, including yield assessments Page 29 of 39 Metric Justification, Additional Notes: The pilot array will be needed for Subtask 6.2. Results: Planted submitted permits for the demonstration system to the pilot site AHJ. Permits were acknowledged and are under review by the pilot site AHJ. Receipt of the permit is now waiting on the city. Demo system build is contingent on permits. Milestone 2.7.1: Draft report Success Value: Draft completed Assessment Tool / Method of Measuring Success Value: Draft of techno-economic report (in slide format) Verification Process: Draft report (slide format) submitted to DOE and presented to “early stage product council”. Summary of council feedback submitted to DOE. Metric Justification, Additional Notes: Preliminary results will show progress toward final report. Results: Milestone 2.5.4: Bankability report commissioned for a sloped site or a sloped/undulating site (*) Assessment Tool / Method of Measuring Success Value: Orders for bankability report from independent third-party engineering firms Verification Process: Copies of purchase order delivered to DOE Metric Justification, Additional Notes: Bankability assessment will be critical for commercial adoption. Results: Planted kicked off with DNV Energy for the demonstration sites and general bankability overview and delivered the communications to the DOE on time. Milestone 2.6.4: Bankability report commissioned for a site containing small sub-plots (*) Assessment Tool / Method of Measuring Success Value: Orders for bankability report from independent third-party engineering firms Verification Process: Copies of purchase order delivered to DOE Metric Justification, Additional Notes: Bankability assessment will be critical for commercial adoption. Results: Planted kicked off with DNV Energy for the demonstration sites and general bankability overview and delivered the communications to the DOE on time. Milestone 2.7.2: Customers engaged Success Value: ≥ 2 Assessment Tool / Method of Measuring Success Value: Count of potential customers to show customer engagement toward meeting EOP-D, as reflected in e-mail exchanges showing interest Verification Process: Copies of redacted emails sent to DOE showing system size(s) and business alignment on project costs Metric Justification, Additional Notes: Documents progress toward securing firm orders. Page 30 of 39 Results: Planted submitted documentation demonstrating engagement from 2/2 customers, including one 11.4MW project and one 847kW project. During the Q2 2025 reporting period, Planted made continued progress towards EOP milestones through repeated small-scale installation demonstrations proving out installer machine and array functionality as well as operational repeatability. Numerous software upgrades were made to both the installer machine and layout tool improving ease of use for field operations. Planted also made significant progress on a new grass maintenance robot tailored for use under the Planted array. Given that the Planted array is shorter than typical tracker systems, the typical approach of human-operated mowers is impractical. This new remotely operated solution dramatically increases the bankability of the system and customer interest. Progress has continued on permitting for the demo system. The project’s EPA permit by the state of Illinois has been approved. The city of Elgin has approved the project’s electrical permit. The zoning permit is pending. Three installer machines operating simultaneously during testing Q3 2025 Reporting Period Planned Milestones vs Accomplishments: Due to the project pause while the DOE reviewed the continuation application, the milestone schedule was updated to move all milestone due dates back by two months. Therefore, the End-of-Project milestones became due after the end of the original project period. Page 31 of 39 Milestone EOP-A Tech: Yield of post placements on sloped demo system Success Value: ≥ 99% Assessment Tool / Method of Measuring Success Value: Pilot system utilizing Planted Solar technology, built on a sloped site (*), completed with high yield for post placement (posts that conform to the array’s mechanical design tolerances, as specified in QA metrics from MS 1.1.A) and do not require re-work due to positioning error. The demo system will include at least 1000 posts. Verification Process: Relevant excerpts from engineering documentation delivered to DOE Metric Justification, Additional Notes: Success of the award will be measured by successful pilot of application of Planted Solar’s technology platform to undulating/sloped terrain. Results: Planted completed pilot system foundation construction with >99% post placement Milestone EOP-B Tech: Area coverage Success Value: ≥ 70% Assessment Tool / Method of Measuring Success Value: Coverage by modules, as documented in engineering drawings, of small/irregular sub-plots (*) within a larger pilot system utilizing Planted Solar technology (excluding perimeter setbacks from calculations) Verification Process: Relevant excerpts from engineering documentation delivered to DOE, with relevant sub-plots indicated and with calculations of their area coverages Metric Justification, Additional Notes: Success of the award will be measured by successful pilot of application of Planted Solar’s technology platform to small/irregular plots. Results: Planted completed pilot system construction with >70% area coverage Milestone EOP-C Costs: Projected LCOE advantage vs. standard (manual, non-automated PV BOS technology) Success Value: > 20% Assessment Tool / Method of Measuring Success Value: Median advantage for 10+ case analyses of scenarios with undulating/sloped terrain and/or small/irregular plots (LCOE advantage compared with the best commercially available alternative array design for each case.) Verification Process: Techno-economic report delivered to DOE Metric Justification, Additional Notes: Success of the award will be measured by the clear cost advantage of the technology. Results: Planted projected LCOE advantage vs. standard PV BOS technology > 20% Milestone EOP-D Stakeholder: Firm orders Success Value: ≥ 10 MW-DC Assessment Tool / Method of Measuring Success Value: Sum of project sizes for which Planted Solar has firm orders, distributed across two or more distinct orders Page 32 of 39 Verification Process: Redacted copies of contracts or letters of intent delivered to DOE—information to be retained in DOE submission to include: name of customer, title of customer contact, location of site, size of PV array, target completion date, termination clauses Metric Justification, Additional Notes: Success of the award will be measured by successful technology transfer to private entities. Results: Planted provided redacted copies of contracts or letters of intent for > 10MW-DC Summary of Planned vs Actual Milestone Deliveries Milestone Schedule SOPO/TWP Original Revised Milestone Description Actual Milestone # Planned Planned Quality management Plan: Gantt chart 1.0.1 8/31/2023 8/31/2023 8/31/2023 with buffers, QA/QC Leading competitive conventional PV 1.3.1 9/29/2023 9/29/2023 9/30/2023 array designs (*) identified Site examples containing small 1.2.1 10/31/2023 10/31/2023 10/31/2023 sub-plots identified 1.2.2 QA metrics for topographic data 10/31/2023 10/31/2023 10/31/2023 1.2.3 QA metrics for array layout software 11/30/2023 11/30/2023 11/30/2023 Examples of topographic data fusion 1.1.1 12/29/2023 12/29/2023 12/31/2023 passing QA metrics Leading competitive conventional PV 1.3.2 12/29/2023 12/29/2023 12/31/2023 array designs analyzed Identification of project site(s) intended 1.1.2 for pilot project: a sloped site or a 1/31/2024 1/31/2024 1/31/2024 sloped/ undulating site (*) QA metrics for array mechanical 1.1.3 1/31/2024 1/31/2024 1/31/2024 parameters Tests conducted to demonstrate correct 1.2.5 operation of array layout software for 1/31/2024 1/31/2024 1/31/2024 small sub-plots Identification of project site(s) intended 1.2.6 for pilot projects: a site containing 1/31/2024 1/31/2024 1/31/2024 small sub-plots (*) Simulated examples showing that topographic mapping and array 1.1.4 planning capabilities result in arrays 2/29/2024 2/29/2024 2/29/2024 that pass the QA metrics defined in MS 1.1.3 1.2.4 Control test for software performance 3/29/2024 3/29/2024 3/29/2024 Page 33 of 39 All key parameters for LCOE 1.3.3 4/30/2024 4/30/2024 4/30/2024 assessments Interviewed vendors in supply chain 1.4.2 4/30/2024 4/30/2024 4/30/2024 relevant to DEI goals Members recruited to informal “early 1.3.4 5/31/2024 5/31/2024 5/31/2024 stage product council” GNG-A Tech Yield of accurate post placements 5/31/2024 5/31/2024 5/31/2024 Yield of acceptable module GNG-B Tech 5/31/2024 5/31/2024 5/31/2024 attachments Completion time to create a layout with GNG-C Tech area utilization comparable to manual 5/31/2024 5/31/2024 5/31/2024 design by an engineer Signed contracts with customers who will build two pilot arrays: one project GNG-D on a site that is a sloped site or a 5/31/2024 5/31/2024 5/31/2024 Stakeholder sloped/ undulating site and one project on a site that contains small sub-plots (*) Projected LCOE advantage vs. standard GNG-E Cost 5/31/2024 5/31/2024 5/31/2024 PV technology Qualified vendors in supply chain for GNG-F DEI recurring services with high growth 5/31/2024 5/31/2024 5/31/2024 potential Demo system designed for a sloped site 2.5.1 9/27/2024 11/29/2024 11/26/2024 or a sloped/ undulating site (*) Demo system designed for a site 2.6.1 9/27/2024 11/29/2024 11/26/2024 containing small sub-plots (*) All permits needed for construction of 2.5.2 12/27/2024 2/28/2025 8/30/2025 first demo system issued by AHJ All permits needed for construction of 2.6.2 12/27/2024 2/28/2025 8/30/2025 second demo system issued by AHJ Demo systems completed for a sloped 2.5.3 2/28/2025 4/30/2025 9/30/2025 site or a sloped/ undulating site (*) Demo system completed for a site 2.6.3 2/28/2025 4/30/2025 9/30/2025 containing small sub-plots (*) 2.7.1 Draft report 2/28/2025 4/30/2025 4/30/2025 Bankability report commissioned for a 2.5.4 sloped site or a sloped/ undulating site 3/28/2025 5/30/2025 5/31/2025 (*) Bankability report commissioned for a 2.6.4 3/28/2025 5/30/2025 5/31/2025 site containing small sub-plots (*) 2.7.2 Customers engaged 4/30/2025 6/30/2025 6/30/2025 Yield of post placements on sloped EOP-A Tech 8/29/2025 9/30/2025 9/30/2025 demo system Page 34 of 39 EOP-B Tech Area coverage 8/29/2025 9/30/2025 9/30/2025 Projected LCOE advantage vs. standard EOP-C Costs (manual, non-automated PV BOS 8/29/2025 9/30/2025 9/30/2025 technology EOP-D Firm orders 8/29/2025 9/30/2025 9/30/2025 Stakeholder Significant Accomplishments and Conclusions Throughout the project, Planted Solar achieved substantial progress in transforming solar deployment from a construction project into a streamlined manufacturing process, particularly addressing the challenges of sloped/undulating and small/irregular sites. Key Positive Outcomes and Significance: ●​ Successfully demonstrated a technology that: ○​ Streamlines project planning and engineering and reduces project completion time by ~50%; ○​ Reduces the amount of steel used by ~70%; ○​ Generates 2-3X more energy per acre ○​ Increases siting flexibility and reduces land use competition by better exploiting irregularly shaped plots, undulating terrain (without the need to grade/fill it), and brownfield sites; and ○​ Reduces levelized cost of electricity (LCOE) by at least 20%, typically 25+%, and up to ~30% if land is expensive, or if the site has challenging terrain features or soil conditions. ●​ Completed the project on-time and on-budget, making efficient use of DOE funding and private funding matching. ●​ Automated Installation Efficiency (GNG-A & GNG-B): The project successfully demonstrated a post placement accuracy of ≥99% on sloped/undulating terrain (over 200 posts) and an acceptable module attachment yield of ≥99% (over 200 modules). This is highly significant as it validates the core premise of automated, efficient assembly in challenging environments, drastically reducing the need for rework and accelerating deployment. This capability directly mitigates the inefficient construction processes, making solar installation faster and more reliable. ●​ Advanced Site Layout Software (GNG-C): Planted Solar's automated layout creation for small/irregular sub-plots achieved completion in less than 5 minutes, with comparable area utilization to manual engineer designs. This is a crucial breakthrough for maximizing Page 35 of 39 energy generation on "non-prime" or constrained land. It significantly reduces design time and cost, making previously uneconomical sites viable and increasing siting flexibility, which is a key public benefit. ●​ Strong Customer Engagement and LCOE Advantage (GNG-D & GNG-E): Securing signed contracts for pilot arrays on sloped and small sub-plot sites (GNG-D) demonstrates strong market interest and acceptance of Planted's innovative approach. Furthermore, the preliminary techno-economic report showing a >10% LCOE advantage for Planted technology on pilot projects (GNG-E) is a critical indicator of commercial viability. This economic benefit directly addresses the high project costs limiting LCOE reductions and reinforces the path towards broad commercial adoption of clean energy. ●​ Product Bankability and Certification: The completion of UL2703 certification for the array technology is a significant step towards meeting industry standards and is a keystone for bankability review. Contracting with DNV Energy for a comprehensive bankability report further strengthens the commercialization potential by providing independent validation of the technology's financial attractiveness. This helps de-risk investments for future deployments. ●​ Operational Refinements and Innovation: Continuous improvements to the post installer machines and array product designs, informed by GNG demos and extensive small-scale demonstrations, highlight a robust development process. The rigorous updates to O&M procedures, including module maintenance and installation guidelines, and compatibility testing with major module manufacturers, directly enhance the long-term viability and attractiveness of Planted's solution. The development of a new grass maintenance robot specifically for high-density arrays underpins the commitment to addressing practical O&M challenges and further boosts bankability and customer interest. Challenges Encountered and Lessons Learned: The primary challenge encountered under this award was permitting delays by external entities for the demonstration systems (Milestones 2.5.2, 2.5.3, 2.6.2, 2.6.3, and EOP milestones). Despite Planted Solar submitting permits on time, the review and approval process by Authorities Having Jurisdiction (AHJ) and local city departments (e.g., for electrical permits, zoning) extended beyond the planned timeline, pushing back the completion of the demo system builds. Lessons Learned: ●​ Factor in Extended Permitting Timelines: The project highlighted the critical need to significantly buffer timelines for external regulatory processes, especially for novel technologies that may require additional scrutiny or education for local authorities. ●​ Contingency Planning for Field Demonstrations: Future project planning should incorporate more flexible schedules for physical demonstrations, acknowledging that these are often contingent on external approvals. This could involve parallel work Page 36 of 39 streams where possible or pre-identifying alternative sites with potentially faster approval processes. Pivots or Reduction in Scope: As noted in the "Project Objectives" section, Task 4.0 was removed due to an executive order. In conclusion, the project has largely met its ambitious objectives, delivering significant technical advancements and demonstrating clear pathways to commercialization. The challenges encountered, primarily external permitting delays, underscore the importance of robust project management and proactive engagement with regulatory bodies in future large-scale deployments. The successful development of high-density racking, terrain-following software, and installation automation positions Planted Solar as a leader in accelerating solar deployment by reducing LCOE, increasing siting flexibility, and mitigating technical risks. Path Forward As a result of the development assisted by this award, Planted Solar now has a technology and customer base ready to deploy solar energy at scale. The path forward will focus on commercial deployment. Planted will install solar for customers across the United States. Additional future development may include: ●​ Increased reliability of the technology ●​ Upgraded machines with higher levels of autonomy ●​ Upscaling the organization and tools for increased deployment demand ●​ Upscoping or partnering with organizations to include energy storage systems in deployments ​ Remaining technical risks to commercialization and broad deployment of cheap, clean energy include the industry-wide risk of loss of business due to federal tax incentive changes and changes to foreign policy impacting solar panel prices. However, Planted’s low-cost low-steel solution will remain industry-leading in its space efficiency, deployment speed, and cost advantages, and therefore is expected to continue to be more commercially viable than other technologies. Products ●​ Planted Solar Installation Machine ●​ Planted Solar Array Racking ●​ Planted Site Layout Software Page 37 of 39 All products’ inventions preceded this DOE award. The DOE award contributed greatly to their continued improvement specifically with respect to increased access to solar energy on sloped/undulating sites, small/irregular sites, and sites with significant sub-surface risks. No publications/papers, scientific data, websites, or patents were created as a result of this work. A poster, “Enabling lower LCOE and increased site flexibility with integrated design software, high density racking, and installation automation,” was presented at the SETO conference and is publicly available under OSTI-ID 2337683. No public awards or results were released as part of this process. Collaboration with the risk management company DNV was a part of this award in supporting the creation of a bankability report. Project Team and Roles Participants and Collaborating Organizations PARTICIPANTS Name Richard Erb Project Role PI Product requirements, engineering management, and Contribution to Project structural analysis, hydrological analysis Name Eric S. Brown Project Role Business Officer Product requirements, stakeholder and customer Contribution to Project engagement, technoeconomic analysis, DEI engagement Name Emma France Project Role Other Professional Systems engineering, structural analysis, environmental Contribution to Project reliability and certification, hydrological analysis Page 38 of 39 References https://www.nrel.gov/analysis/solar-futures https://www.paces.com/reports/renewable-energy-trends-edition-3-site-selection-for-sol ar Page 39 of 39