FINAL TECHNICAL REPORT APRIL 13,2026 Methane Mitigation Using Linear Motor Leak Recovery Compressor FINAL TECHNICAL REPORT Methane Mitigation Using Linear Motor Leak Recovery Compressor Principal Investigator: Jason Stair, GTI Energy Other Key Personnel: Devin Halliday, GTI Energy Michael Lewis, UT Austin Center for Electromechanics Ray Zowarka, UT Austin Center for Electromechanics START: April 1, 2020 END: March 31, 2026 Prepared by GTI ENERGY ▪ UT-CEM for Department of Energy under contract DE-FE0031875 Jason Stair 04/13/2026 Devin Halliday 04/13/2026 Michael Lewis 04/09/2026 Principal Engineer Principal Engineer Director GTI Energy GTI Energy The University of Texas at Austin - Center for Electromechanics GTI Energy Business Contact: GTI Energy Principal Investigator: Penny Dubernat, Contracts Manager Jason Stair, Principal Engineer TABLE OF CONTENTS Acknowledgement .......................................................................................................................................................... ii Disclaimer.......................................................................................................................................................................... iii EXECUTIVE SUMMARY ............................................................................................................................................. 1 INTRODUCTION ............................................................................................................................................................ 3 Background ...................................................................................................................................... 3 Project objectives ........................................................................................................................... 4 METHODS......................................................................................................................................................................... 6 PROJECT RESULTS AND DISCUSSION ........................................................................................................ 10 Techno Economic Analysis ..................................................................................................................................... 23 SIGNIFICANT ACCOMPLISHMENTS AND CONCLUSIONS .................................................................. 28 PATH FORWARD ....................................................................................................................................................... 31 PRODUCTS ................................................................................................................................................................... 34 PROJECT TEAM AND ROLES ............................................................................................................................. 35 GLOSSARY ................................................................................................................................................................... 36 LIST OF TABLES AND FIGURES ........................................................................................................................ 37 TABLES ......................................................................................................................................... 37 FIGURES ...................................................................................................................................... 37 REFERENCES ............................................................................................................................................................. 38 Page ii This page is intentionally left blank. Page 1 EXECUTIVE SUMMARY GTI Energy (GTI), in collaboration with The University of Texas at Austin - Center for Electromechanics (UT‑CEM), designed, fabricated, and tested a linear motor–driven compressor intended to mitigate methane emissions at natural gas facilities across transmission, storage, gathering, and processing sectors of the gas value chain. The technology was developed to capture low-pressure vented methane from multiple emission sources—including compressor seals/rod packing vents, pneumatic device vents, and planned operational events such as blowdowns—and compress the recovered gas back to pipeline pressure, thereby reducing emissions while retaining product value. Methane mitigation at compressor stations is challenging because a meaningful fraction of emissions can originate from components and operating events that are intermittent, distributed, or difficult to route to conventional recovery systems (e.g., blowdowns and certain vented sources). Compressor rod packing vents, pneumatic devices, and blowdowns among key contributors to lost gas that would be addressed by this solution. The project included dynamic simulation and modeling, preliminary and detailed design, prototype fabrication and integration into a test skid, and commissioning and testing activities. Quarterly reporting documented that the compressor was fully assembled, installed, commissioned, and tested using nitrogen, before subsequently being tested with natural gas. Testing focused on the flow control required to maintain attached vent systems near atmospheric pressure, while demonstrating that the compressor could also reach midstream discharge pressures between 1,000 to 1,500 psig. Economic feasibility was also treated as a core requirement throughout the project. The system economics are highly dependent on the site operating conditions, specifically emphasizing compressor utilization and discharge pressure as key drivers of payback and capital cost. Overall, the development was successful, and a promising prototype was designed and tested. However, the compressor still requires additional testing and improvement to fully validate that the performance can translate to the field. Page 2 This page is intentionally left blank. Page 3 INTRODUCTION Background Methane is the primary component of natural gas and a valuable energy source, making mitigation of methane emissions a national priority with economic and public benefit implications. Annually, an estimated ~7,600 kilotons of methane are lost during oil and gas production. [Reference 1] Assuming a Henry hub price of $3, that is $1.2 billion of natural gas lost annually. Studies of these emissions indicate that they are concentrated in a few locations that include oil production (18%), gas production (42%), and gas transmission and storage facilities (19%). [Reference 1] Common methane sources relevant to this project include: • Compressor seals, rod packing and wet/dry gas seals, are found on every compressor from production to transmission and storage. These seals leak continuously under normal operation and increase leakage as components wear. Estimates of the total impact vary, but most sources agree that they make up a large fraction of the total emissions found across the value chain. • Pneumatic controllers and other gas-actuated devices are used widely in production, gathering/boosting, and transmission/storage settings, which can vent methane during continuous bleed operation or actuation. These devices are considered by many to be one of the largest sources of emission due to their widespread use. • Blowdowns and maintenance-related venting, where pressurized gas is released for safety and operational reasons. Safety related blowdowns are difficult if not impossible to recover; however, maintenance related blowdowns can be recovered and compressed downstream if planned for ahead of time. There are a number of existing solutions to these emissions; however, they are often expensive, are designed to address one emission source, and may only offer an emission reduction rather than complete mitigation. For example, the best recommendation for rod packing is simply maintenance. Dry gas seals are a replacement for wet seals but still emit gas. Even other vapor recovery compressors have a limited discharge pressure, so they are only suitable at low pressure sites or must deliver the gas to the fuel system of a nearby engine or generator, assuming it is running. In place of these partial solutions, the team proposed a central methane recovery utility where all emitted methane can be captured and compressed back to pipeline pressure for complete recovery. This simple, direct solution allows sites to keep all their existing equipment, recovers all emissions directed to the recovery compressor, and has zero impact on the site equipment as the emissions are compressed back into the pipeline, rather than into an engine or other key piece of equipment. How This Project Advances the State of Practice Page 4 This project accomplished the proposed approach using a linear motor compressor architecture intended to provide (1) broad operating flexibility, (2) rapid controllability to match dynamic leak rates, (3) high discharge pressures suitable for reinjection into pipeline systems, and (4) a sealed, oil-free design intended to reduce maintenance burdens and avoid introducing new leak points. This specialized compressor was integrated into a leak recovery system that would only require power, connection of all vent systems to the inlet buffer vessel, and a discharge connection to the pipeline or storage system. With these simple site modifications, the recovery compressor would automatically maintain the connected vent systems near atmospheric pressure, regardless of the vent gas flow rates, ensuring that all connected equipment still worked as intended and that all vented emissions could be safely and efficiently recovered. Project objectives The objective of this project was to design, build, and test a high-pressure methane leak recovery compressor capable of cost-effectively capturing and recovering methane emissions from natural gas facilities across the transmission, storage, gathering, and processing segments of the natural gas value chain. The technology was intended to address methane emissions that are typically vented to atmosphere during normal operations or maintenance activities, including emissions from compressor seal systems, pneumatic devices, and planned operational events such as blowdowns. A core motivation for this effort was the lack of a commercially viable, purpose-built solution capable of recovering low-pressure, variable-flow methane emissions and returning that gas directly to high-pressure pipeline systems without disrupting normal facility operations. Primary Technical Objectives The primary technical objective of this project was to develop and demonstrate that the linear motor–driven methane leak recovery compressor could operate over the wide range of pressures and flow conditions characteristic of vented methane emissions at natural gas facilities. The compressor was required to accept methane at near-atmospheric inlet pressures and compress that gas to high discharge pressures representative of transmission, storage, gathering, and processing systems. Achieving this pressure ratio within a single, integrated recovery system was essential to enable direct reinjection of recovered methane without intermediate handling or modification of existing facility equipment. A second objective was to demonstrate precise and reliable control of compressor operation to support safe integration with vented emission sources. Many methane leaks and vents originate from systems that are not designed to tolerate backpressure, and therefore the recovery compressor needed to dynamically match incoming flow while maintaining inlet pressures within a narrow, safe operating range. The project sought to show that a linear motor–driven compressor, coupled with appropriate control logic, could respond to changing inlet conditions in real time without pressurizing upstream equipment or disrupting normal facility operations. Page 5 In addition to pressure control, the project aimed to demonstrate operational flexibility across highly variable emission profiles. Methane emissions at natural gas facilities can range from small, continuous leaks to large, short-duration releases associated with planned operational events such as blowdowns. The compressor system was therefore designed to operate efficiently over a broad turndown range, allowing it to ramp output up or down as needed without hardware changes or manual intervention. This flexibility was a critical requirement for enabling recovery of emissions from multiple sources using a single, centralized system. Another key technical objective was to minimize maintenance requirements and secondary emissions through careful system design. The project pursued a sealed, oil-free compressor architecture intended to reduce wear, eliminate the need for lubricating oil, and avoid introducing additional fugitive emission points. By limiting the number of moving parts and simplifying mechanical interfaces, the design sought to improve reliability and reduce lifecycle operating costs relative to conventional compression technologies. This simplified design was then installed in a sealed housing designed to eliminate any additional emissions from the recovery compressor itself. Collectively, these technical objectives were intended to demonstrate not only that methane recovery from low-pressure vent sources is technically feasible, but that it can be accomplished in a manner that is safe, responsive, and compatible with real-world natural gas facility operations. Success in meeting these objectives would establish a foundation for broader deployment of leak recovery compressors as a practical methane mitigation strategy across the natural gas value chain. Page 6 METHODS Overview of Technical Approach The project employed a staged development and validation methodology to design, construct, and evaluate a linear motor–driven methane leak recovery compressor suitable for application at natural gas facilities. The methodological approach combined engineering analysis, dynamic simulation, prototype fabrication, control system development, and pilot-scale testing to ensure that the system could meet the functional, safety, and operational requirements associated with recovering low-pressure methane emissions and reinjecting that gas into high-pressure pipeline systems. The work was structured to progressively reduce technical risk by first validating performance assumptions through modeling and component-level testing, followed by full system integration and controlled experimental evaluation. At each stage, design decisions were informed by the need to balance performance, reliability, operational flexibility, and cost, with the overarching goal of demonstrating a technically viable and deployment-ready methane mitigation solution. System Design and Architecture Compressor Concept and Operating Principle The leak recovery system is based on a linear motor–driven reciprocating compressor architecture. Unlike conventional crankshaft-driven reciprocating compressors, the linear motor directly actuates the piston, eliminating the need for rotary-to-linear mechanical conversion. This architecture enables precise control of piston motion, including stroke length, speed, and frequency, which is essential for managing variable inlet conditions and maintaining stable operation over a wide range of flow rates. The compressor was designed to accept methane at near-atmospheric inlet pressures representative of vented emission sources and compress the gas to discharge pressures suitable for reinjection into natural gas pipelines operating at pressures up to 1,500 psig. Three stages of compression were used to achieve the required pressure ratio, each driven by an independent linear motor. This modular design was selected so that the compressor could be adapted to any site operating conditions simply by adding or removing stages to reach the site’s operating pressure or adding/removing motors to adapt to the site’s expected flow rates. Leak Recovery System Integration The compressor was integrated into a complete leak recovery system that included safety and monitoring equipment, inlet piping and filtration, interstage cooling and filtration, discharge piping, power electronics, instrumentation, and a centralized control system. The system was configured to accept gas from one or more vented sources and route recovered methane directly to a high-pressure outlet. Particular attention was paid to inlet design to ensure that upstream vent systems would not experience unacceptable backpressure during operation. Page 7 The system architecture was intentionally modular to support future adaptation to different facility configurations and to facilitate testing, maintenance, and potential field deployment. Modeling and Design Analysis Dynamic Simulation and Performance Modeling Dynamic modeling and simulation in Matlab Simulink were used to guide key design decisions related to compressor sizing, motor selection, staging configuration, and control strategy. Simulations evaluated system performance across a range of inlet pressures, flow rates, and discharge pressures to ensure that the compressor could meet the expected operating envelope associated with vented methane emissions. The modeling effort focused on predicting piston dynamics, compression thermodynamics, power consumption, and control responsiveness under variable conditions. These analyses informed design tradeoffs related to stroke length, operating frequency, and motor force requirements, as well as expected efficiency and thermal behavior. Design Iteration and Optimization Simulation results were used iteratively to refine mechanical design features, including piston geometry, sealing arrangements, and staging layout. Design optimization emphasized achieving sufficient compression capability while minimizing mechanical complexity and reducing wear. The final design balanced performance requirements with manufacturability and reliability considerations. Component Development and Subsystem Testing Linear Motor and Drive System The linear motor and associated drive electronics were developed and evaluated to confirm their ability to deliver the required force, speed, and positional accuracy across the intended operating range. Testing focused on validating motor responsiveness, controllability, and thermal performance under representative operating conditions. Motor characterization informed the final control algorithms and ensured that the motor could support rapid changes in operating state without loss of stability or excessive power consumption. Compression Components and Sealing Compression components, including pistons, cylinders, valves, and seals, were fabricated and assembled to meet the mechanical and thermal demands of multi-stage compression. Sealing strategies were selected to minimize leakage and wear while avoiding the use of lubricating oil. The oil-free design was intended to reduce maintenance requirements and prevent contamination of recovered gas. Control System Development Page 8 Control Objectives A central element of the project methodology was the development of a control system capable of managing compressor operation in response to changing inlet conditions. The primary control objectives were to: • Maintain inlet pressure within a narrow, safe range to prevent pressurization of upstream vent systems, • Adjust compressor throughput dynamically to match variable methane flow rates, • Ensure stable operation across the full operating envelope, and • Protect equipment through appropriate interlocks and safety logic. Control Architecture and Implementation The control system was implemented using an industrial programmable logic controller (PLC) interfaced with sensors measuring pressure, temperature, flow, and motor position. Control algorithms modulated piston motion parameters in real time to regulate compressor performance. Feedback control loops were designed to respond to changes in inlet pressure and flow, allowing the system to ramp output up or down as conditions changed. Safety features included pressure limits, emergency shutdown logic, and fault detection routines to ensure safe operation during testing and anticipated field use. Pilot-Scale Testing Methodology System Assembly and Integration Following component-level validation, the compressor and all supporting subsystems were assembled into a fully integrated leak recovery system. Electrical, mechanical, and control interfaces were verified during assembly to ensure compatibility and correct operation. The system was prepared for testing in a controlled environment representative of industrial conditions, including hazardous-area considerations and appropriate isolation of power electronics. Commissioning and Test Configuration The assembled system was commissioned in a controlled test environment. Initial testing was conducted using inert gas to verify mechanical integrity, control functionality, and overall system stability without introducing flammable gas hazards. Commissioning activities included leak checks, sensor calibration, control tuning, and verification of safety systems. Following successful inert gas commissioning, the system was prepared for operation with natural gas to evaluate performance under representative process conditions. The system was purged with natural gas, then tested across a range of operating conditions. Test Objectives and Measurements Page 9 Pilot-scale testing was designed to evaluate the following aspects of system performance: • Ability to accept gas at near-atmospheric inlet pressure without imposing excessive backpressure, • Capability to achieve target discharge pressures, • Responsiveness to changes in inlet flow rate, • Power consumption under varying operating conditions, • Stability of control during steady-state and transient operation. Instrumentation recorded pressures, temperatures, flow rates, motor position, and electrical power to support performance evaluation and analysis. Data Collection and Analysis Test data was collected continuously during operation. Performance metrics were evaluated against the project objectives to assess whether the system met design expectations. Observed deviations were used to identify opportunities for control refinement and design improvement. Economic Assessment Methodology In parallel with technical development, an economic assessment framework was applied to evaluate potential deployment scenarios. The methodology examined capital cost drivers, energy consumption, and recovered gas value under representative operating conditions. Sensitivity analyses explored how utilization rate and discharge pressure requirements influence economic performance. The economic assessment was intended to inform design prioritization and identify pathways for improving cost-effectiveness through future optimization and scale-up. Methodological Summary Through a combination of modeling, controlled experimentation, and system-level integration, the project methodology was designed to rigorously evaluate the feasibility of a linear motor–driven leak recovery compressor for methane mitigation. The approach emphasized technical rigor, operational realism, and alignment with the practical constraints of natural gas facility operations. Page 10 PROJECT RESULTS AND DISCUSSION The overarching goal of the project was to simulate, design, build, test, and validate a linear motor methane leak recovery compressor capable of capturing low-pressure methane emissions and compressing them back to pipeline pressures, while maintaining safe inlet pressures at connected vent systems. A summary of the anticipated and realized outcomes is listed below. Anticipated versus realized performance: • Target inlet / suction pressure: The compressor inlet was designed for 0-0.25 psig (target range for connected vent systems set by industry partner); Testing used a suction pressure of ~0.25-0.5 psig. This slightly higher pressure was used during testing to prevent a suction pressure switch from inadvertently shutting down the compressor when gathering performance data and has minimal impact on the actual performance of the unit. The compressor will operate down to atmospheric pressure in the field. • Target discharge pressure: The compressor discharge pressure was designed for 1,000-1,500 psi. The compressor reached 1,500 psig, but most testing was done at 1,100-1,250 psi to reduce the load on the system and prevent the discharge safety shutdowns from triggering. • Target flow: The simulation demonstrated ~50-60 SCFM from atmospheric inlet to 1,500 psi discharge. The measured flow was about 36-38 SCFM. The shortfall is the result of several factors that include higher than expected internal leakage back to the compressor suction at 8-10 SCFM, a supply voltage of 400Vac instead of 480Vac that reduced the system speed, and motor control tuning that can continue to be improved over time. Minor changes to the motor construction, supply voltage, seals, and controls should result in a significant increase in the flow. The most significant change is the use of a drop-in low- inductance motor that would increase the system speed by up to 2.5x, increasing the flow to 90-100 SCFM. • Controls / flow matching demonstration: The compressor was designed to rapidly adjust for flow changes so that the suction pressure was maintained between 0-0.25 psig. The target pressure used during testing was 0.5 psi to demonstrate flow control and avoid shutdowns caused by the suction pressure switch. The compressor held the suction pressure well within 0-1 psig despite the flow alternating between about 5 and 35 SCFM. This demonstrated that the design can rapidly adapt to changes in the methane leak flow rate and the team is confident that this control can be improved with further testing. • Safety readiness for natural gas testing: The safety and monitoring equipment were installed and tested (including shutdowns, oxygen monitoring, suction protection), prior to switching to natural gas. Page 11 Overall, the compressor is achieving or close to achieving each of the target metrics. The team is confident that the flow and suction pressure control will continue to be improved beyond the scope of this project as these compressors are deployed for field use at operational gas production, processing, storage, and transport facilities. Task-Level Results Milestone Log – Smart CNG Station Deployment Budget Period 1 – April 1, 2020 – March 31, 2021 Planned Actual Milestone Title Method of Completio Completi Comments Verification n Date on Date Goal: Update and confirm the Project Management Plan based on DOE comments and any changes since the 1.1 Finalize 4/30/2020 6/30/2020 DOE approval funding application was PMP submitted. Progress: Completed, PMP was submitted and approved DOE Goal: Update and confirm the Technology Maturation Plan based on DOE comments and 1.2 Finalize changes since the funding Technology 5/31/2020 6/30/2020 DOE approval application was submitted. Maturation Plan Progress: Completed, TMP was submitted and approved by DOE Goal: Prepare and operate simulation of compressor system to identify size of components (pistons, chambers, valves, etc.) and 2.1 Preliminary Design meets their operating characteristics Simulation atmospheric (speed, load, etc.) to satisfy Meets Flow and9/30/2020 9/30/2020 inlet to >1000 output requirements (P, flow) Pressure psi discharge Progress: Completed, Requirements simulation was modified to represent methane leak recovery system and has been updated throughout the execution of the project. Page 12 Goal: Motor and compressor 2.2 Preliminary Images of designs frozen with proper Design 3/31/2021 3/31/2021 complete component sizes, materials, Complete models. and seals. Verify Goal: Verify that motor and fluid 2.3 Key simulation and ends can reach targets for Component component speed and flow at acceptable 12/31/2020 6/30/2021 Performance test data show operating limits for T and P and confirmed reasonable force loads. agreement. Progress: Completed Goal: Laboratory versions of Images of 2.4 Test motor and compressor 3/31/2021 9/5/2025 complete test Apparatus Built hardware built. apparatus. Compressor Goal: Cost for motor and 2.5 Economic cost is compressor designs are Analysis Shows reasonably estimated using vendor or Promise for 3/31/2021 3/31/2021 aligned with catalog quotes. Cost/benefit Commercializat other methane analysis computed for leak ion mitigation mitigation. technologies. Progress: Completed Budget Period 2 – April 1, 2021 – September 30, 2022 Goal: Data from tests of motor Validated test and compressor are reliable 3.1 Testing and data and match performance performance reasonably simulation within limits. verification agrees with Progress: GTI has requested 9/30/2021 3/31/2026 meets expected that this milestone be moved to simulated performance BP3 so that the compressor can performance from be tested in parallel with the simulation. complete leak recovery skid. Complete. Images of leak recovery Goal: Complete leak recovery system design system is designed including 3.2 Detailed including gas source, gathering Design 3/31/2022 9/30/2022 modifications hardware, compressor, motors, Completed to and discharge tank. underperformi Progress: Complete. ng components. Budget Period 3 – October 1, 2022 – March 31, 2026 Page 13 Goal: Final fabrication and 4.1 Prototype Images of assembly of the complete linear Fabrication and 12/31/2022 9/5/2025 complete motor leak recovery Assembly assembly. compressor is complete. 4.2 Design and Goal: The Recipient will design Build Test and build a test apparatus for Images of Apparatus testing and validating the 12/31/2022 9/17/2025 complete (Continuation performance of the linear motor assembly. from Budget leak recovery compressor. Period 2) Progress: Completed 4.3 Preliminary Goal: The linear motor leak Fabrication, recovery compressor design will Testing, and Test data will be tested to validate that the Validation 3/31/2023 3/31/2026 be recorded actual performance meets the (Continuation and reported. simulated performance. from Budget Period 2) Goal: The Recipient will verify Test data will operation in a relevant be recorded, environment that matches real- 4.4 Pilot-Scale and world conditions for the leak 9/30/2023 3/31/2026 Testing performance recovery compressor including evaluated in verifying the controls and safety reports. features are working properly. Goal: The project team will complete a final economic and The economic performance analysis of the 4.5 Final analysis will be pilot-scale tested prototype to Economic 9/30/2023 3/31/2026 updated and verify the system cost and Analysis finalized. performance meets the needs of industry stakeholders. Key Challenges and Design Iterations The linear motor and compressor designs went through multiple iterations as the team worked to balance the performance, design flexibility, manufacturability, and other key design characteristics. Some of the most significant changes are described below. 1) The original compressor design had 4 stages of compression driven by a single linear motor. The design used 4 stages to ensure the discharge gas for each stage was kept relatively cool to help extend the life of the seals and valves. However, the team was ultimately forced to move to 3 stages of compression to Page 14 enable the use of a double acting stage 1 within the single linear motor configuration. This change was deemed necessary after extensive simulation of the compressor and leak recovery system showed that the suction pressure would be impossible to control within the specified limits without a double acting stage 1 to constantly pull in gas from the supply. While this change was made early in the project, it still delayed the design which could not proceed until the simulation had fully validated the performance of the system. 2) After settling on the 3-stage design, the team began working on the model of the compressor. One of the key components that needed to be selected were the piston seals. The team had previously used lip seals in prototype compressors, so that was the default choice for the design. Unfortunately, after designing the fluid ends for lips seals, the lip seal vendor no-bid the design. This forced the team to search for a new seal supplier. After identifying a new vendor, seals suitable for the operating conditions were designed, but these seals required more real estate than the original lip seal design. This forced the team to make extensive changes to the compressor design to fit the new seals into the model. 3) After the seal redesign, the team provided the piston geometry to Cook Compression to evaluate and finalize the valve design. Their extensive industry experience and models indicated that there would be a flow imbalance between the compression stages. This took some time and effort to validate. Ultimately, the team determined the problem was real and that the compressor fluid ends would need to be modified again to address the compression imbalance. The new design simplified the compressor stages by moving from double acting pistons to two single acting pistons for each stage of compression. These modified designs were evaluated again and ultimately approved by Cook Compression who could then finalize the valve design. 4) At this point, all the stages of compression were still integrated into a single motor. However, GTI had started working with additional industry partners that made it clear that the original motor design was oversized for most sites and that it needed to be easily scalable for different site operating conditions as no two gas facilities are the same. The change didn’t require a compressor redesign but did require that each stage be separated and driven by smaller, independent motors. This change had the added benefit of reducing the operational vibration as the multiple motors could be operated out of phase. The final design consisted of four linear motor assemblies driving three stages of compression. Each stage of compression was powered by one motor assembly. The fourth linear motor was operated without a compressor fluid end attached but was used to balance the system dynamics and test additional bearing configurations in the motor assembly. The team considered circling back to the four-stage design that was originally conceived, but that would have caused additional delays, so that idea was abandoned. Figure 1 shows the final solid model of a single linear motor and compressor assembly. The hermetically sealed motor is located at the center of the assembly with the stage 1 Page 15 compression pistons attached to either end of the motor. This design was developed because it was highly modular, making it easy to change the stroke length and power of the linear motor and compressor. The assembly was also designed to be hermetically sealed up to pressures exceeding 1,500 psig, making the design useful for applications beyond methane recovery. The hermetically sealed design also prevents any seal leakage from venting to atmosphere. Instead, all seal leakage was routed from the linear motor housing, back to suction where it was simply captured and compressed. Figure 2 shows the complete compressor assembly installed in GTI Energy’s environmental chamber inside a Class 1 Div 2 test area. The assembly closest to the camera is stage 1. The 2” piping on the left side of the image is the suction that is supplying the stage 1 piston on either end of the assembly. The suction piping was later connected to the discharge of a filter that was used to catch any liquids and solids before the gas entered the compressor. The other motors and compression stages were all mounted on a single skid along with stage 1. The skid was designed so that the entire four motor assembly could easily be moved around using a standard forklift. Figure 3 shows most of the balance of plant components including the intercoolers, filters, and control valves that were used to control the compressor discharge pressure and simulated leak rates. Not shown are the suction buffer vessel that was located just outside the environmental chamber, the suction filter that was located next to the compressor, and the oxygen sensor that was located on the wall out of view. The compressor was designed to operate like it would out in the field. It drew gas in from the suction buffer vessel and compressed it up to the target discharge pressure. The compression was evenly split between 3 stages, each included intercoolers, filters, pressure sensors, and temperature sensors. The discharge pressure was controlled between 0 to 1,500 psig using a flow control valve that would stay shut until the target discharge pressure was reached. Then the control valve would open enough to maintain the target discharge pressure at whatever flow the compressor was currently producing. Downstream of the discharge control valve, there was an intermediate buffer vessel that operated between 50-150 psig. The intermediate buffer vessel supplied a second flow control valve that was used to simulate methane leaks. This was accomplished by opening or closing the valve to predetermined setpoints. These setpoints changed the effective orifice of the valve and therefore the amount of gas that could “leak” from the intermediate buffer to the suction buffer. The setpoints used during testing resulted in leaks that alternated between about 5 and 35 SCFM every 10 seconds. These leaks were operated completely independently from the compressor control loop, so the team could demonstrate that the compressor was in fact able to independently react to changes in the leak flow rate. The goal of the compressor controls was to change the speed of the compressor in real time so that the pressure of the suction vessel was held between 0-0.25 psig despite the rapid changes in flow feeding the suction vessel. If the compressor ran too fast, then the buffer vessel would drop in pressure and the compressor risked drawing in air that could create a flammable mixture inside the compressor or pipeline. If the Page 16 compressor ran too slowly, then the buffer vessel pressure would rise, risking over pressurization of any connected equipment that was venting natural gas. The team was able to hold the suction pressure between 0-1 psig during multiple step changes in flow. The team is happy with these results but will continue to improve the performance until the design can meet the target set by an industry partner Figure 1: Solid model of Figure 2: Complete compressor Figure 3: Balance of plant compressor and one linear motor assembly installed in GTI Energy flow loop components installed in GTI assembly driving a test cell. Energy test cell. compression piston at either end of the assembly. The compressor was fully instrumented so results from the testing are well documented. Each stage of compression was instrumented with pressure and temperature sensors on the suction and discharge of the stage. Figure 4 through Figure 6 show the results from each of the three stages of compression during a leak recovery test. The stage 1 suction is near 0 psig while the discharge fluctuates around 50 psig. Between 50 and 60 seconds, and again between 70 and 80 seconds, these fluctuations become spaced out because the leak rates supplying the compressor have slowed, causing the compressor to also slow down. Page 17 The gas leaving stage 1 is cooled using a liquid cooled intercooler before returning to stage 2. The stage 2 suction is about 45-50 psig and about 34F. It is then compressed Page 18 Figure 4: Stage 1 performance during methane leak recovery testing. Figure 5: Stage 2 performance during methane leak recovery testing. Page 19 Figure 6: Stage 3 performance during methane leak recovery testing. to a little more than 250 psig and 200-225F. The fluctuations in flow are harder to make out from the discharge pressure, but the discharge temperature rises as the flow speeds up and falls slightly as the compressor slows down. Stage 3 is the final stage and compresses the gas from about 250 psig to about 1250 psig, the setpoint for this test. The suction temperature was about 35 F and the discharge fluctuated between about 175F to 200F. Again, the temperature fluctuates as the flow increases and decreases during the test. Figure 7 shows the compressor flow and suction pressure during the test. The top half of the graph shows two flow rates. In orange, the compressor discharge was measured in kg/hr which is a close approximation of SCFM. This is the gas flow that was actually captured and compressed through all three stages of compression, back to pipeline pressure. In other words, this is the recovery flow rate. However, during compression, the piston seals leaked more than expected. These leaks flowed past the seals to the sealed motor housing and then were piped back to the compressor suction. The flow rate of these leaks is shown in dark blue, measured in SCFM. These leaks are an inevitable part of any compressor, but in the case of the hermetically sealed leak recovery compressor, they are just an efficiency loss as all the gas is directed back to suction for recovery. On the bottom half of the graph is the suction pressure which is held between 0 and 1 psig. This is despite the rapid changes in flow seen in the top half of the graph. The suction pressure control was accomplished using a simple PI controller that influenced Page 20 the speed of the compressor. As the suction pressure rose above the 0.5 psig setpoint, the compressor would rapidly speed up until the pressure dropped below 0.5 psig where it would slow down again. This control is a little easier to see in Figure 8 where the x- axis has been reduced from 50 seconds to 3 seconds. The suction pressure signal is easier to see, including the impulses caused by the compressor quickly reciprocating. Around 50,500 ms, the suction pressure begins to dip below 0.5 psig. Shortly after 51500 ms, the compressor nearly stopped, and the pressure slowly started to rise. It’s at this point when we also see the discharge flow, which lags slightly behind the compressor motion, start to drop back towards zero. The compressor then starts up again around 52500 ms as the suction pressure starts to approach 0.5 psig. Figure 7: (TOP) The compressor discharge flow rate (kg/hour) is pictured along with the leak rate past the piston seals. The leaks are captured and recirculated back to the compressor suction. (BOTTOM) The suction pressure is shown in parallel to the step changes in flow. Despite the step changes in flow, the compressor is able to maintain the compressor suction well within 0-1 psig. Page 21 Figure 8: Zoomed in view of the suction pressure, discharge flow, and leak flow rates. These results demonstrate that the compressor is operating as intended and is able to quickly adjust to a wide range of rapidly changing leak rates that might be found as operational gas facilities. This flexible operation and the hermetically sealed design allow the compressor to recover all vented emissions from these facilities so that the gas is not lost but is instead recovered and transported to end users. The project team also measured the compressor power and efficiency during the leak recovery testing. Figure 9 shows the variable flow on the top of the graph and the real time power on the bottom of the graph. A moving average was added to the power traces to make them easier to interpret. The average power at peak flow is about 20kW, but then quickly drops with the flow, maintaining a reasonable efficiency during recovery of the methane emissions. The isentropic efficiency of the compressor at peak flow is 45-50% which is reasonable for a compressor at this scale, but could be further improved by reducing leaks, friction, and increasing the speed of the compressor so that it can run closer to resonance. These changes could add 10-20% to the compressor’s efficiency and nearly triple the flow rate. Page 22 The isentropic efficiency of the entire test was about 35%. The compressor itself is still reasonably efficient as the flow decreases. However, as the flow decreases towards the internal seal leak rate, then compressor is eventually just internally circulating the gas leaking by the seals, consuming power without recovering any gas. This results in a minimum practical leak rate that can be recovered by the unit and will influence how the compressors need to be sized for a particular site. The internal leak rate is driven by the pressure in the compression stages and not the flow of the discharge. So as the team works to speed up the compressor, the leak rate is expected to remain relatively constant and will become a smaller percentage of the maximum flow and less of an issue. Further, there are potential design changes to the fluid ends and seals that can be made to help reduce the internal leakage. Ultimately, this is not a fundamental barrier to the technology, but an engineering issue that can be improved with incremental changes to the design. Figure 9: The compressor flow and power are pictured. The moving average of the power helps to show how the power is dropping along with the flow which helps to minimize the power consumed during methane recovery. Page 23 TECHNO ECONOMIC ANALYSIS The technoeconomic analysis (TEA) performed in this study was developed using the H2FAST Financial Analysis Scenario Tool created by the National Laboratory of the Rockies (NLR) [Reference 2]. It is to be noted that the inputs to the tool on the “Interface” tab were adjusted to suit the scope of the project and the equipment considered. The inputs and assumptions utilized in the analysis are detailed in the subsequent sections of this document. Capital Cost Estimation Methodology The project team developed estimated costs of “Primary Equipment” that comprise the methane leak compressor unit. The costs considered in this analysis were based on the estimated costs once 100 units have been produced. The “Primary Equipment” cost for a three-stage unit was taken to be 3 times the cost of the “Primary Equipment” included in the single-stage system. To develop an “installed” cost for the unit, the following cost adders were considered in addition to the baseline “Primary Equipment” costs: • Miscellaneous consumables: 10% of “Primary Equipment” Cost • Fabrication & Assembly: 10% of Primary Equipment Cost & Miscellaneous Consumables • Installation Labor: $8,000 (both single-stage and three-stage systems) o 2 Personnel, Full Time for 1 Week (80 hours total), at $100/hr. • Gas Piping Connections: o Single-stage System: 10% of “Primary Equipment” Cost o Three-stage System: The piping connections for the three-stage system are the same as a single-stage system as the piping headers are a common connection, so the assumed cost was kept the same as the single-stage system. • Electrical Connections: o Single-stage System: 6% of “Primary Equipment” Cost o Three-stage System: The electrical connections for the three-stage system are the same as a single-stage system, so the assumed cost was kept the same as the single-stage system. • Profit: 20% of “Primary Equipment” cost and all other additional cost factors. Additional assumptions considered in the analysis are as follows: Page 24 • Costs for land and civil infrastructure were not included in this cost estimate. It was assumed that the compressor unit would be installed at a brownfield facility with existing infrastructure. • Capital costs were assumed to be paid up front, no debt or spreading of capital expenditures were considered. Operating Cost Estimation Methodology The key assumptions and methodology utilized to calculate the fixed and variable operating costs for the scenarios evaluated are listed in the following subsections. System Availability & Runtime: • The compressor unit is assumed to be operational 8,592 hours per year. o It is assumed that 1 week of downtime is required each year for maintenance. Operating Parameters • Natural Gas Capture Rate: o Low Flow Case: 36 kg/hr o High Flow Case 65 kg/hr • Electricity Consumption: o Low Flow Case: 17.5 kW o High Flow Case: 31.6 kW (assumed to scale linearly with capture rate) Pricing & Cost Assumptions Pricing assumptions utilized in this analysis are presented in Table 1. Table 1: Recovered Product Value & Utility Costs Parameter Price Units Source/Notes Recovered Product Price on 3/19/2026 Natural Gas – Hub $3.21 $/MMBTU Price Error! Reference source ($0.16) ($/kg) not found. Electricity Page 25 Industrial Sector – Q1 2026 Electricity – Industrial $0.086 $/kW-hr Error! Reference source Users not found. Fixed Operating Costs The following assumptions were considered with respect to fixed operating costs: • Maintenance costs for the system were estimated to be $5,000 per year for the single-stage system and $15,000 per year for the three-stage system. • Direct labor was not considered in the evaluation of fixed costs as no additional labor costs are associated with direct operation of the compressor. • Insurance costs and property taxes were not considered in this analysis. General Methodology & Financial Assumptions The economic viability of the unit was evaluated through the calculation of two parameters: 1. Calculation of the levelized cost of recovered natural gas using the Discounted Cash Flow (DCF) method. This represents the breakeven price that the recovered product would need to be sold for in order to break even at the end of the unit’s operating life. 2. The payback period for the unit was calculated based on the market value of the recovered product gas. Additional financial assumptions considered in the TEA modeling are as follows: • The dollar year basis considered for this evaluation was 2026 dollars. • A discount rate of 13% was assumed (H2FAST default). • A constant rate of inflation of 2% per year was considered (H2FAST default). • The operational life of the methane leak compressor was assumed to be 25 years. • No recovered capital costs/revenues were considered at the end of the operating life. • Depreciation: o Depreciation Type: MACRS o Depreciation Period: 7-year Period (typical for machinery assets) Page 26 • Taxes on revenue were not considered in this analysis as it is understood that the recovered natural gas is not actually sold as a product that generates taxable income, but rather provides value by offsetting losses. • Capital Gains Tax: 0% (Capital Gains were not applicable to this analysis) • A Working Capital fund was not considered in this analysis, as it was deemed to not be applicable for this type of system. • Installation Period: 1 month o H2FAST requires that a period for installation be specified. The minimum value that can be specified is 1 month, and therefore an installation period of 1 month was assumed. This installation period takes place at the start of the unit’s operating life. Other parameters not explicitly mentioned in this document were kept as default values specified in H2FAST. Sensitivity Analysis The economic evaluation performed using the H2FAST tool included a sensitivity analysis to identify the influence of key parameters on the levelized cost of recovered natural gas and the calculated payback period. The parameters that were varied in the analysis and the ranges of variation applied were as follows: • Natural Gas Market Price: +/- 25% • Electricity Price: +/- 25% • Maintenance Cost: +/- 25% • Capital Cost: +/- 25% • Discount Rate: +/- 15.38% (corresponding to discount rates of 11% & 15%, respectively) TEA Results The team assessed the economics of the following design cases. 1) Low flow case: This case used early flow and performance results from the unit that was tested at GTI (36 kg/hr / 17.5 kW). The payback period was estimated to be about 12 years. 2) High flow case: This case used the target flow and scaled the power consumption linearly (65 kg/hr / 31.6 kW). The payback period was 6 years. Page 27 3) Low flow and low-pressure case: This case assumed the unit achieved the flow as tested (36kg/hr), but that the site only needed a single stage of compression to enable recovery of the gas. The payback period was estimated at 4 years. The results are not unfavorable considering the compressor was designed to be durable and repairable with an equipment lifespan easily exceeding 20 years. However, it’s clear that improving the flow can drastically lower the expected payback period as more performance can be achieved for little to no impact on the capital cost of the equipment. The following changes are being considered to improve the flow and have little to no impact on the capital cost of the design. For starters, the supply voltage is 400 Vac instead of 480Vac. This is because the team used an existing isolation transformer that dropped the 480 supply to 400 volts. By using the more common 480 Vac supply, the existing motors will be able to operate about 15-20% faster, resulting in 15-20% more flow. This is a simple change that would have essentially zero impact on the capital cost and may even lower the cost if the isolation transformer can be eliminated entirely, which is being considered The second change would be to improve the controls and system software. There are several changes being considered that could theoretically be made to the controls and power electronics that would add an additional 15-20% to the speed and flow of the existing design. These changes are still conceptual, but it’s possible that the flow could be further improved just by modifying the compressor’s software that would have zero cost once implemented. The last and most impactful change would be to modify the motor design. By winding the motor with a larger gauge of wire and fewer turns, the motor inductance could be reduced, significantly increasing the top speed of the motor at a given supply voltage. The tradeoff is that the motor would also require more current to achieve the same force, so while the low inductance motor would likely cost about the same amount as the current motors, the drive would need to get slightly larger. However, the drive only makes up a small fraction of the capital cost, and the flow has a direct impact on the payback period, so this trade would likely have a net benefit. Some improvements to the controls have already been made since the TEA was evaluated. For example, the flow used in the TEA was 36 kg/hr, but the compressor has achieved peak flows of 40-43 kg/hr at an average speed of 1.25 m/s. By further improving the power electronics and bus voltage, the speed can theoretically be increased from ~1.25 m/s to ~1.8 m/s, resulting in a flow of about 55-60 kg/hr, close to the original target. By making the additional changes to the motor windings, it should be possible to reach speeds in excess of 3 m/s and a flow rate of 90-100 kg/hr, demonstrating that there is significant room for improved performance and therefore significant potential to improve the system economics and payback period, making the methane recovery compressor an attractive solutions for operational gas facilities across the country. Page 28 SIGNIFICANT ACCOMPLISHMENTS AND CONCLUSIONS Overview This project successfully demonstrated the technical feasibility of methane leak recovery using a linear motor–driven compressor, validating a novel compression architecture for capturing low-pressure methane emissions and returning that gas to pipeline-relevant pressures. The work progressed from simulation through detailed design, fabrication, commissioning, and pilot-scale testing, establishing a clear performance baseline while identifying targeted pathways for improvement and commercialization. While not all original performance targets were fully achieved, the results confirm that the core recovery concept functions as intended and that remaining gaps are engineering-limited rather than fundamental. This distinction is significant for assessing technical readiness and future investment decisions. Significant Technical Accomplishments Demonstration of High-Pressure Methane Recovery Capability A major accomplishment of the project was demonstrating that the linear motor compressor architecture can compress gas from near-atmospheric inlet conditions to discharge pressures up to 1,500 psi, enabling reinjection into pipelines at pressures relevant to most midstream facilities. This directly addresses a key barrier to methane mitigation—namely, the lack of practical solutions for recompressing low-pressure vented gas back into operating pipelines. The ability to reach these pressures confirms that the compressor can be customized or staged to meet site-specific pressure requirements across a wide range of transmission, storage, gathering, and processing applications. This flexibility is a core advantage of the linear motor architecture and significantly expands the potential deployment envelope compared to fixed-speed, mechanically constrained compressors. Validation of Variable Leak-Rate Matching and Suction Pressure Control Another critical accomplishment was the demonstration of variable-speed operation capable of matching changing leak rates while maintaining safe suction pressures. Testing showed that the compressor could respond to aggressive step changes in leak rates while keeping the inlet pressure close to atmospheric conditions. This capability is essential for real-world deployment because many upstream vent systems can tolerate only minimal backpressure. By maintaining accurate suction pressure control despite rapid changes in inlet flow, the compressor prevents over-pressurization of connected equipment and avoids creating new safety hazards. The results confirm that the linear motor’s fine motion control provides a meaningful operational advantage over conventional compression approaches in leak recovery applications. Hermetically Sealed, Oil-Free Operation with Natural Gas Page 29 The project also successfully demonstrated a hermetically sealed compressor design, an important accomplishment for emissions control and safety. Leak checks using handheld flammable gas detectors verified that the compressor enclosure remained sealed during operation. The compressor was operated using natural gas, further validating its suitability for the intended working fluid. During testing, the motor housing experienced internal pressures on the order of 10–20 psig, and the system continued to operate as intended. This confirms the robustness of the sealed design and supports the conclusion that the compressor does not introduce additional fugitive emission pathways—an essential requirement for any methane mitigation technology. Confirmation of Overall Leak Recovery Functionality Taken together, the pressure capability, suction control, and sealed operation demonstrates that the unit can accomplish methane leak recovery as designed. The compressor was shown to accept low-pressure gas, dynamically adjust to changing inlet conditions, and deliver compressed gas suitable for reinjection, validating the fundamental recovery concept that motivated the project. This outcome is significant because it establishes a working prototype that can be refined rather than requiring a redesign of the underlying approach. Performance Gaps, Challenges, and Lessons Learned Flow Rate Shortfall and Identified Improvement Pathways The most significant performance gap identified during the project was lower-than-target flow capacity. While simulations predicted 50–60 SCFM, measured flow during testing was approximately 36 SCFM. Contributing factors included operation at reduced motor speed and higher-than-expected internal leakage (on the order of 8–10 SCFM). Importantly, these limitations were not attributed to fundamental constraints of the linear motor architecture. Instead, the project identified clear pathways for increasing flow, including: • Increasing motor speed through improved control algorithms, • Raising DC bus voltage, • Implementing alternative motor windings, • Applying more advanced PWM control strategies, and • Incorporating additional compression stages where appropriate. This distinction is critical: the shortfall reflects an engineering optimization opportunity, not a failure of the core concept. Power Consumption and Efficiency Considerations Power consumption was monitored throughout testing using integrated instrumentation and industrial control systems. While the project did not fully optimize energy efficiency, the data collected provided a foundation for future improvements. As with flow rate, Page 30 efficiency is expected to improve as internal seal leakage is reduced, motor utilization increases, and controls are refined to better match real-world leak dynamics. Controls Complexity and Development Sequencing Developing controls capable of both protecting upstream equipment and maximizing compressor throughput proved to be a non-trivial challenge. Early testing relied on conservative configurations to ensure safety, which limited achievable speed and flow. The project demonstrated that more advanced control strategies—particularly those that decouple leak simulation valves from compressor control—are necessary to fully validate autonomous leak-matching performance. This experience highlighted the importance of controls development sequencing and reinforced that control sophistication is as critical as mechanical design in methane recovery applications. Economic Considerations and Commercialization Outlook Economic analysis conducted during the project indicates that the leak recovery concept is promising but highly sensitive to flow rate and manufacturing scale. Increasing flow directly improves economic performance by increasing recovered gas value and reducing payback time. Similarly, scaling manufacturing is expected to significantly reduce unit costs through learning curves and supply-chain optimization. Planned cost-reduction strategies therefore focus on: • Increasing achievable flow through design and controls improvements, and • Transitioning from prototype fabrication to scalable manufacturing approaches. Overall Conclusions This project successfully demonstrated that a linear motor–driven compressor can recover methane emissions safely, responsively, and at pressures suitable for reinjection into midstream infrastructure. The compressor met its most critical functional requirements—pressure capability, suction control, sealed operation, and dynamic response—while revealing specific areas for performance optimization. The results support the conclusion that the technology is technically viable and well-positioned for further development, with remaining challenges concentrated in flow optimization, controls refinement, and cost reduction rather than fundamental feasibility. As such, the project provides a strong foundation for subsequent engineering refinement and potential field deployment of methane leak recovery systems based on linear motor compression. Page 31 PATH FORWARD Overview The results of this project establish a strong technical foundation for methane leak recovery using a linear motor–driven compressor, while also clearly identifying the remaining engineering, economic, and deployment steps required to advance the technology toward commercialization. Future work should focus on performance optimization, cost reduction, and field-representative demonstrations to transition the system from a successful pilot-scale prototype to a commercially deployable solution. The technology also shows promise beyond methane mitigation, with potential applicability to hydrogen, air, carbon dioxide, and other compressible gases, further expanding its value proposition across emerging energy and industrial markets. Near-Term Research and Development Priorities Controls and Speed Optimization The most critical near-term R&D priority is further optimization of controls and motor speed capability, as these directly impact flow rate, efficiency, and cost per unit of gas recovered. While the project demonstrated stable variable-speed operation and accurate suction pressure control, additional development is expected to yield substantial performance gains. Key areas for future work include: • Increasing achievable motor speed through refined control algorithms, • Expanding the operating envelope using higher DC bus voltage, • Evaluating alternative motor windings optimized for higher flow operation, • Implementing advanced pulse-width modulation (PWM) strategies to improve motor efficiency and responsiveness, and • Refining autonomous leak-rate matching logic to better reflect real-world vent dynamics. Improvements in these areas are expected to simultaneously increase flow capacity, reduce specific energy consumption, and lower the effective cost of methane recovery per unit volume. Mechanical Refinement and Leakage Reduction Internal seal leakage identified during pilot testing represents another important opportunity for improvement. Future design iterations should focus on refining sealing strategies to reduce internal losses, thereby increasing net recovered flow without increasing power input. Expanded Application Opportunities Natural Gas Recovery and Methane Mitigation Page 32 The primary commercialization pathway remains natural gas recovery across upstream, midstream, and storage assets. The demonstrated ability to maintain near-atmospheric suction pressure while compressing gas to pipeline-relevant pressures positions the technology well for recovering emissions from vent systems, compressor seals, pneumatic devices, and planned operational releases. Future deployment efforts should prioritize sites with: • Persistent or recurring vented emissions, • Sufficient discharge pressure requirements to justify recompression, • Existing infrastructure that benefits from centralized recovery systems. Hydrogen Compression The oil-free design of the linear motor compressor makes it particularly attractive for hydrogen service, where contamination is a key concern. With appropriate material selection and sealing optimization, the technology could support hydrogen compression for a variety of applications. The team has demonstrated this capability during the development and testing of a 12,000 psi hydrogen expander. The team is also currently working on a small-scale 6,000 psi hydrogen compressor. Air and Carbon Dioxide Applications Beyond energy applications, the compressor architecture may also be well suited for air and CO₂ compression, including applications related to industrial processes, carbon capture systems, and emissions control. The ability to precisely control flow and pressure over a wide operating range provides flexibility that is attractive in these contexts, particularly where variable demand or intermittent operation is required. Field Demonstration and Deployment Pathways Deployment Projects A logical next step for advancing the technology is a field-based deployment project focused on real-world operating environments. Such a project could take multiple forms, including: • Upstream sites, where low-pressure vented emissions are common and infrastructure is often dispersed, • Midstream compressor stations, where recovered gas can be readily reinjected into high-pressure systems, and • Midstream storage facilities, where intermittent venting events present attractive recovery opportunities. These deployments would serve to validate long-duration reliability, maintenance requirements, and operational integration while providing high-confidence data to support commercialization decisions. Economic Scale-Up and Manufacturing Strategy Page 33 Cost Reduction Through Scale While the prototype system demonstrated technical viability, cost reduction remains a key requirement for widespread adoption. Future efforts should focus on: • Increasing flow capacity to improve economic return per installed unit, • Transitioning from prototype fabrication to repeatable manufacturing processes, and • Leveraging economies of scale in motors, power electronics, and structural components. As production volumes increase, unit costs are expected to decline substantially, improving payback periods and enabling broader deployment across the natural gas value chain. Remaining Technical and Commercialization Risks Despite the strong progress achieved, several risks and barriers remain that must be addressed before immediate commercialization: • Flow and efficiency optimization risk: While improvement pathways are well understood, additional engineering effort is required to fully realize predicted performance gains. • Controls complexity: Advanced autonomous control strategies must be robustly validated under a wide range of real-world operating conditions. • Economic sensitivity: Project economics remain sensitive to recovered flow rates and utilization levels, making performance optimization essential. • Field integration challenges: Site-specific constraints, safety requirements, and operational practices may require customized system configurations. None of these risks are considered fundamental barriers; rather, they represent typical development challenges for transitioning the linear compression technology from pilot scale to commercial readiness. Concluding Outlook The work completed under this award demonstrates that linear motor–driven compression is a viable and flexible platform for methane leak recovery and related gas handling applications. With targeted follow-on R&D focused on controls optimization, leakage reduction, and manufacturing scale-up—combined with carefully selected field demonstrations—the technology is well positioned to advance toward commercialization and to support emissions reduction goals across multiple sectors. Page 34 PRODUCTS No papers or publications outside of DOE reporting. No software was developed under this project. No websites were produced. There are no new patents at this time. The key product from the project is the operational compressor itself. This prototype has significantly advanced and de-risked the technology to the point that it is ready for field deployment. Page 35 PROJECT TEAM AND ROLES o GTI Energy o Compressor design o Flow loop design o System fabrication o System assembly o System commissioning o Testing o University of Texas Center for Electromechanics o Compressor simulation o Validation of simulation and analysis of system performance Page 36 GLOSSARY The following list of acronyms, abbreviations, and terms are applicable for this report: Acronym or Term Definition BP Budget Period DOE Department of Energy F Fahrenheit GTI GTI Energy – Prime contractor kg kilogram kW kilowatt ms Milliseconds NLR National Laboratory of the Rockies PMP Project Management Plan PSI Pounds per square inch PSIG Pounds per square inch – Gauge pressure PWM Pulse width modulation SCFM Standard cubic feet per minute - flow TMP Technology Maturation Plan TEA Technoeconomic analysis UT-CEM The University of Texas at Austin - Center for Electromechanics Page 37 LIST OF TABLES AND FIGURES TABLES Table 1: Recovered Product Value & Utility Costs ..............................................................................................24 FIGURES Figure 1: Solid model of one linear motor assembly driving a compression piston at either end of the assembly. ..................................................................................................................................................................16 Figure 2: Complete compressor assembly installed in GTI Energy test cell. ...........................................16 Figure 3: Balance of plant compressor and flow loop components installed in GTI Energy test cell. 16 Figure 4: Stage 1 performance during methane leak recovery testing. ...................................................18 Figure 5: Stage 2 performance during methane leak recovery testing. ...................................................18 Figure 6: Stage 3 performance during methane leak recovery testing. ...................................................19 Figure 7: (TOP) The compressor discharge flow rate (kg/hour) is pictured along with the leak rate past the piston seals. The leaks are captured and recirculated back to the compressor suction. (BOTTOM) The suction pressure is shown in parallel to the step changes in flow. Despite the step changes in flow, the compressor is able to maintain the compressor suction well within 0-1 psig. 20 Figure 8: Zoomed in view of the suction pressure, discharge flow, and leak flow rates....................21 Figure 9: The compressor flow and power are pictured. The moving average of the power helps to show how the power is dropping along with the flow which helps to minimize the power consumed during methane recovery. ...................................................................................................................22 Page 38 REFERENCES This section lists the references cited in the report: Reference 1: https://www.epa.gov/system/files/documents/2024-04/us-ghg-inventory-2024- main-text_04-18-2024.pdf Reference 1: https://www.nlr.gov/hydrogen/h2fast Reference 2: https://markets.businessinsider.com/commodities/natural-gas-price Reference 3: https://www.eia.gov/outlooks/steo/tables/pdf/7atab.pdf 1700 S. Mount Prospect Rd. Des Plaines, Illinois 60018 www.gti.energy